Modular Rain Garden

Backfilling and Planting

ST

AGE 4

Once the modules have been installed, 

install the observation well, if specified, 

prior to commencing back fill.

Before adding bio-retention fill 

materials, make sure that the site 

is stabilized so that they will not 

be contaminated by excessive 

sedimentation in a storm event.

Backfill the excavated area outside of 

the structure in 8” lifts using crushed 

angular stone and backfill the interior 

of the structure with the prescribed 

fills (sands, aggregates, filter fabrics, 

and planting soils per plan) so that the 

inside and the outside of the system are 

backfilled in alternating lifts.  Remove 

temporary shoring 

Follow the plan specifications for 

material types and layer thicknesses 

of the bio-retention fill materials. 

Do not compact the interior fills, 

and consult the project designer for 

recommendations regarding overfill of 

the planting soils since approximately 

20% more may be required to account 

for natural settlement.

As you backfill the interior, install 

erosion protection at the water intake 

locations.  

Water bio-retention materials and 

allow to settle and adjust heights to 

plan specifications, as required, before 

adding plant materials and final mulch 

layer as specified.

Place plants once soils have settled.  

Add mulch layer to achieve final grade.

Step 9:

 Backfilling structure.

Step 10:

 Placing, Planting Soils.

Erosion control at water intake

Summary of Contents for Freno

Page 1: ...A INSTALLATION MANUAL INSTALLATION MANUAL Modular Rain Garden...

Page 2: ...required to install the system one machine operator and one laborer Each Freno module has built in connection inserts that allow easy attachment to lifting equipment using 3 4 common thread bolts The...

Page 3: ...ions of structures The modules each have lifting connections placed to assist in connecting the system to lifting equipment to facilitate placement of the modules during construction and for potential...

Page 4: ...Endless Options The Freno System allows great flexibility in the construction of a variety of structure configurations because it is a kit of parts Here are several examples of possible configuration...

Page 5: ...the site while under construction and divert traffic dangers away from site workers Pre Construction Site Review Obtain engineering plans for the project and any required permits Note any access rest...

Page 6: ...It may be most efficient to place the plant materials after paving has been completed to avoid repetition of effort since performing the paving work may require access from within the bio retention ar...

Page 7: ...rench as much as possible recommendation regarding amount of over excavation and illustration Rendering of plan view of recommended trench configuration If your system will include an under drain exca...

Page 8: ...a level condition to the elevation specified in the plans The leveling pad should be 18 wide and at least 6 thick after compaction see drawing for typical leveling pad dimensions and placement which...

Page 9: ...pact Excavator capable of lifting _____ lbs Attach the lifting attachments to the Freno Module using the lifting connections Figure ___ that allow connection to bolts with 3 4 common thread Connect th...

Page 10: ...een backfilled but will help assure the modules stay in their proper position during construction To assist in leveling the module a heavy plastic covered mallet may be useful to seat the module and m...

Page 11: ...2 Establish a corner by placing next module Using a second T2 panel install the foundation for the intake structure Confirm this module is level at the right elevation and oriented correctly before m...

Page 12: ...t alignment and elevation as you go Step 4 Once the first side is completed start installing the modules on the other side Step 5 Continue installing Modules on this side Place a connecting rod in the...

Page 13: ...Module to provide proper spacing for placement of the last Side Module Step 7 Install the final side Module Step 8 Install the water intake structures using the N Mod ules as shown in Stage 3 D Here...

Page 14: ...Stage 4 below backfill the exterior of the structure near and around the intake structure with angular crushed stone being careful to assure that the T 2 modules remain correctly aligned and level Pl...

Page 15: ...he system are backfilled in alternating lifts Remove temporary shoring Follow the plan specifications for material types and layer thicknesses of the bio retention fill materials Do not compact the in...

Page 16: ...should not be placed in service until all of the drainage area has been stabilized and approved by the inspector If there will be any delays before paving is completed make sure sediment controls rema...

Page 17: ...leaders in the concrete products industry We offer high performance cost effective products for the construction of buildings stormwater management and low impact development of sites 800 789 0872 ww...

Reviews: