background image

2

Cooper Lighting Solutions    

 IB516115EN

    

 Installation Instructions

Installation Instructions – ClearPath Bollard

Included:

 

1 Foundation Template

 

1 Bollard Housing

 

1 Bollard Cover

 

1 Tamper resistant bollard cover Mounting Screw

 

1 Bollard Base

 

2 Mounting Brackets

 

4 Socket Head Cap Screws

 

4 Flat Washers

 

4 Nylon insert Locking Nuts

 

1 Gap Pad

 

#8 Self-tapping ground screw (green)

Tools required:

Plumb bob or level, torque wrench for the following drive 

sizes:
5/16” Hex drive (Allen) torque wrench,
1/4” Socket
T27 Center pin reject Torx drive.

Installation

tep 1 

S

Prepare the foundation.

There are 3 templates provided in CPBANCHOR 

kit (sold separately). From the 3 foundation 

templates: CLP0012385H01AS, CLP0012385H01AD, 

CLP0012385H01SY, choose the one which matches the 

optical distribution you will install. Use the template to 

locate the foundation bolts such that the light output is 

in the desired direction(s). Install foundation anchors and 

conduit. 

Step 2 

Prepare the bollard.

Use a center pin reject Torx drive to remove the screw on 

the front of the luminaire. Next remove the cover by sliding 

it first towards the top of the luminaire, then away from the 

other half. Set it aside in a safe place. Loosen, but do not 

remove, the four socket head cap screws with a (5/16”) hex 

(Allen) wrench. 

Figure 1.   

Figure 1a.   

Figure 1b. Asymmetric Double Side (CLP0012385H01AD) 

Figure 1c. Asymmetric Single Side (CLP0012385H01AS)

Figure 1d.  Symmetric Double Side (CLP0012385H01SY)

Bolt Projection

Housing Side

Outer Dimension Of 
Bollard 4.7” X 6.3”

Outer Dimension Of 
Bollard 4.7” X 6.3”

Outer Dimension Of 
Bollard 4.7” X 6.3”

HOUSING SIDE

HOUSING SIDE

HOUSING SIDE

COVER SIDE

COVER SIDE

COVER SIDE

Notes: Conduit Must 
Be Inside Of Opening 
With A Height Of 3” 
Max. Above Concrete.

Notes: Conduit Must 
Be Inside Of Opening 
With A Height Of 3” 
Max. Above Concrete.

Notes: Conduit Must 
Be Inside Of Opening 
With A Height Of 3” 
Max. Above Concrete.

Anchor Bolt Projection To 
Be 1” Above Concrete. 
Tolerance ± 1/8”

Anchor Bolt Projection To 
Be 1” Above Concrete. 
Tolerance ± 1/8”

Anchor Bolt Projection To 
Be 1” Above Concrete. 
Tolerance ± 1/8”

Clearpath Bollard 
Anchor Bolt Template 
CLP0012385H01 W/ 
3/8” Dia Anchor Bolts

Clearpath Bollard 
Anchor Bolt Template 
CLP0012385H01 W/ 
3/8” Dia Anchor Bolts

Clearpath Bollard 
Anchor Bolt Template 
CLP0012385H01 W/ 
3/8” Dia Anchor Bolts

Cover Side

Summary of Contents for Invue ClearPath Bollard

Page 1: ...or lighting services and should not be used in area of limited ventilation or inside high ambient temperature enclosures It must be stored in a dry location prior to installation Do not expose lightin...

Page 2: ...remove the cover by sliding it first towards the top of the luminaire then away from the other half Set it aside in a safe place Loosen but do not remove the four socket head cap screws with a 5 16 h...

Page 3: ...inal torque each nut to 30 ft lbs Verify that the base is plumb If not plumb loosen the nuts shim the base as necessary and repeat the torque procedure above Figure 2 Step 4 Install mounting brackets...

Page 4: ...6a Neutral Installation Site Foundation Fixture Leads Fixture Mounting Base White Black Green Line Voltage Ground Figure 6 Field Wiring Diagram Figure 5a Even Gap Between Brackets Bosses In Housing F...

Page 5: ...er next to the installed housing holding the cover roughly one inch higher The cover will engage the housing in this position Slide the cover down to engage the cleat that joins the top of the cover t...

Page 6: ...ns des enceintes haute temp rature ambiante Il doit tre rang dans un endroit sec en attendant son installation N exposez pas le luminaire la pluie la poussi re ou d autres conditions ambiantes avant l...

Page 7: ...luminaire puis l cart de l autre moiti Mettez le de c t dans un endroit s r Desserrez mais ne retirez pas les quatre vis t te cylindrique six pans creux 5 16 po Figure 1 Figure 1a Figure 1 b Double fa...

Page 8: ...urez vous que la base est d aplomb Si un cart de verticalit est pr sent desserrez les crous calez la base si n cessaire et r p tez la proc dure de serrage ci dessus Figure 2 tape 4 Installation des su...

Page 9: ...fondation Fils de luminaire Base de montage du luminaire Blanc Noir Vert Tension compos e Mise la terre Figure 6 Sch ma de c blage sur place Figure 5a M me espace entre les supports et les bossages d...

Page 10: ...itier install en le tenant environ un pouce plus haut Le couvercle entra nera le boitier dans cette position Faites glisser le couvercle vers le bas pour engrener la clavette qui relie le dessus du co...

Page 11: ...s de ventilaci n limitada o en lugares cerrados a alta temperatura ambiente Debe almacenarse en un lugar seco antes de la instalaci n No exponga el accesorio de iluminaci n a la lluvia el polvo u otra...

Page 12: ...seguro Afloje pero no quite los cuatro tornillos de cabeza hueca con una llave hexagonal Allen 5 16 in Figura 1 Figura 1a Figura 1b Doble faz asim trica CLP0012385H01AD Figura 1c Simple faz asim trica...

Page 13: ...ete cada tuerca definitivamente a 30 ft lb 40 67 N m Verifique que la base est a plomo Si no est a plomo afloje las tuercas calce la base seg n sea necesario y repita el procedimiento de apriete que s...

Page 14: ...stalaci n Terminales de la luminaria Base de montaje de la luminaria Blanco Negro Verde Voltaje de l nea Conexi n a tierra Figura 6 Diagrama de cableado en campo Figura 5a Espacio uniforme entre los s...

Page 15: ...osteni ndola aproximadamente una pulgada 2 54 cm m s arriba La cubierta encajar en el alojamiento en esta posici n Deslice la cubierta hacia abajo para enganchar la abrazadera que une la parte superio...

Page 16: ...rferencias da inas en una instalaci n residencial Este equipo genera usos y puede emitir energ a de radiofrecuencia y si no se instala y utiliza de acuerdo con las instrucciones puede causar interfere...

Reviews: