Installation Instructions
1. Floor should be level +/- 1/16”. If not, each cabinet must be shimmed.
Note:
Anchoring optical lanes to an uneven ground most likely will cause serious
issues in unit operation.
2. Install conduit for 100-240 VAC to primary cabinet, conduit for access control
integration (if applicable), and a conduit in between the primary and secondary cabinet
for cabling to the secondary cabinet. Lane distance can be varied from 22 to 38 inches.
3. With each cabinet in the exact position to be mounted, use a center
punch to mark location of the four holes to be drilled in the floor.
Note:
Make sure each cabinet is square to each other, otherwise operation will be
inconsistent
3. If necessary, move cabinets out of the way. Drill four 3/8” holes 4” deep per
cabinet and remove all concrete dust from the holes.
4. Place cabinet in the correct location and install SS wedge type anchors
supplied. Torque the nuts to a minimum of 50 foot pounds.
5. Plug the power supply in the main cabinet into 100-240 VAC (single phase) minimum
3 amp GFI circuit.
6. The sensors we use are a thru-beam type: they require a transmitter and
receiver in order to operate. In order to accomplish this, you must connect
24VDC power to the secondary cabinet. This is accomplished with a provided two
conductor cable. See the wiring diagram for more information.
Security Begins With Controlled Access
1636 W. 130th Street, Brunswick, OH 44212
Toll Free Phone: (800) 942-0829 | Fax: (800) 942-0828 / Phone: (330) 273-6185 | Fax: (330) 273-4468