The humidification system Condair DL may be commissioned and operated only by persons familiar with
the humidification system Condair DL and adequately qualified. It is the owner’s responsibility to verify
proper qualification of the personnel.
4.1
First-time commissioning
The first-time commissioning must always be done by a Condair representative or factory trained ser-
vice technician. Therefore, the current manual does not provide de tail ed infor ma tion on this procedure.
The following steps are carried out upon first-time commissioning in the specified order:
• Inspecting the humidification unit, the control unit and the central unit for correct installation.
• Inspecting the electrical installation
• Inspecting the water installation
• Flushing the water supply line and testing the water quality.
• Checking direction of rotation of the booster pump and adjusting the speed of the booster pump.
• Checking whether the spray circuits are connected to the corresponding nozzles and that all nozzles
are spraying correctly.
• Configuring the control unit or the humidification system Condair DL, respectively.
• Carrying out test runs.
• Fill in the commissioning protocol.