3. Commissioning
Page 18
MF0150A4A.doc Manual for ION-M7P/17EHP/19P
3.1.3. Wall-Mounting
Procedure
Notice:
It is the responsibility of the installer to verify that the supporting surface will
safely support the combined load of the electronic equipment and all attached
hardware and components and to ensure that the RU is safely and securely
mounted.
1. Mark the position of the drilling
holes (for pitches refer to figure
3-1 Wall mounting). Drill four
holes at the marked positions and
insert dowels*.
2. Mount the brackets (A) to the wall
using the M8x80 screws (B), split
lock washers (C), and washers
(D).
figure 3-1 Wall mounting - pitches
3. Hang the Remote Unit into the upper
bracket, insert it to the lower bracket, and
fasten it to the lower bracket with the
M8x25 screws (E), split lock washers (F),
and washers (G).
* The dowels are not included with the delivery because the suitable type depends on the on-site
conditions (material of wall).