4.

 

Install alarm wiring.

 On the left side of the 

panel, there is an 8p8c modular jack (RJ-45) 
for alarm connections. The pinout is: 

 

 

5.

 

Install output feeds.

 First, land the return cable lug to its corresponding position on the return bus bar, then land the 

hot cable lug to the corresponding position above. 

6.

 

Install circuit breakers.

 Turn the captive panel mounting screws counterclockwise and remove the front panel. Slide a 

circuit breaker of sufficient ampacity into the position corresponding to the output channel to be fed (viewing the front 
of the panel from left to right, the positions are A1, A2, A3, A4, A5, A6, A7, A8, then B1, B2, B3, B4, B5, B6, B7, B8). Push 
until the circuit breaker terminals are fully seated in the sockets. 

Installation Checklist 

 

Rack mount ears mounted securely to the panel and the rack? 

 

Chassis ground cable connected? 

 

Input power cables (A Hot, A Return, B Hot, B Return) securely bolted to the correct bus bars and heat shrink installed? 

 

Alarm cable connected and wired correctly to remote monitoring device (if required)? 

 

Output feed cables landed to correct polarity? 

 

Wire lacing or cable ties installed to provide strain relief? 

 

Breakers installed in the correct positions and fully seated? 

 

 

Summary of Contents for Matrix 016-131-10

Page 1: ...Matrix 1RU High Power Density DC Distribution Center SETUP AND OPERATION MANUAL S E T U P A N D O P E R A T I O N M A N U A L...

Page 2: ...ed at the factory to withstand the normal rigors of shipping However you should carefully inspect the box and contents to confirm that no damage occurred in transit Most shipping carriers require noti...

Page 3: ...rack use the two holes further back on the sides of the panel 2 Install the chassis ground cable A chassis ground cable should be landed on the two studs marked Chassis Ground on the left side of the...

Page 4: ...on corresponding to the output channel to be fed viewing the front of the panel from left to right the positions are A1 A2 A3 A4 A5 A6 A7 A8 then B1 B2 B3 B4 B5 B6 B7 B8 Push until the circuit breaker...

Page 5: ...ory Button The Breaker Inventory Button when held for more than five seconds is used to store the breaker inventory in nonvolatile memory The button may also be used to temporarily silence indefinitel...

Page 6: ...is turned off the red Breaker Trip LED will turn on and the alarm beeper will sound When the breaker is turned back on the LED will turn off and the alarm beeper will silence 4 The breaker inventory...

Page 7: ...successful Panel and Breaker Rating Limitations The panel is rated for a maximum current of 300A per bus The sum of the eight distribution breakers on either side of the panel may not exceed 300A The...

Page 8: ...ine Breakers Each slimline breaker has two threaded brass screw hole features designed for extraction The breaker extraction tool is fitted with screw features designed to attach to the breaker Attach...

Page 9: ...sory controller LED status indicator only About Comm net Systems Comm net Systems Inc CSI is the leader in high power density communications power systems Comm net offers comprehensive power and commu...

Reviews: