2.12 Electrical connections
The power cable must be connected to a 230V (±10%) ~ 50 Hz
network, observing L-N polarity and the earth connection.
The network must have an omnipolar switch with category III
overvoltage, in compliance with the installation rules.
If this cable needs to be replaced, an original spare must be
requested from
Climit
.
Therefore only the connections of the original components
as shown in the table are needed. These are to be ordered
separately from the boiler.
DESCRIPTION
CODE
External sensor kit (ß=3435, NTC 10KOhm at 25°C)
8094101
Power cable (dedicated)
6323875
Remote control HOME (open therm)
8092280
Remote control HOME PLUS (open therm)
8092281
m
CAUTION
The maintenance interventions described must ONLY
be carried out the professionally qualified personnel.
a
WARNING
Before carrying out any interventions described:
– set the main system switch to "OFF"
– close the gas valve
– make sure that no hot parts inside the appliance are
touched.
OFF
Fig. 14
To facilitate introduction of the connection wires of the optional
components into the boiler:
– remove the screws (1), pull the front panel (2) forwards and
release it from the top by lifting it
2
1
Fig. 15
– remove the screws (3) securing the control panel (4)
– move the panel (4) upwards (a) but keeping it in the side
guides (5) to the end of travel
– bring it forwards and down (b) until it is horizontal
3
a
b
4
5
Fig. 16
– insert the connection wires into the cable gland (6) and the
opening (7) on the control panel
6
7
Fig. 17
– bring the control panel (4) to the original position and secure
it with the screws (3) which were removed previously
– connect the component wires to the terminal board (8)
following the indications provided on the data plate (9).
3
4
8
9
SE
CR-TA
6
5
4
3
Fig. 18
Summary of Contents for 24 OF
Page 114: ...114 ...
Page 115: ...115 ...
Page 116: ...Via Garbo 27 37045 Legnago Vr Tel 39 0442 631111 Fax 39 0442 631292 ...