Installation Instruction

Figure. 1

L=50±5mm

5.1 Post and  Girder Installation 

5. Installation Instruction

Prepare the required installation tools and products 
before installation.

As per engineering drawings, mark out the positions 
for bolts and embed 4pcs of M20 bolt in each 
position as shown in Figure 2. 

Make sure all M20 bolts are aligned in both 
horizontal and vertical direction. All embedded bolts 
will be revealed 50±5mm above the ground as 
shown in Figure 1.

Note: The M20 bolts and matching nuts, washers 
and spring washers are provided by installer.

 

As shown in Figure 3, place bolts M12*35 into H 
Joint 130/240.   

5.1.1 

5.1.2

Figure. 3

Figure. 2

Installation Instruction

According to the engineering drawing, slide H Joint 130/240 to the corresponding position on the Girder and 
lock it as shown in Figure 4.

For sliding smoothly, to ensure the plane of the M12 bolt cap be parallel to the Girder slot surface when H 
Joints slide into the Girder, as shown in Figure 5.

Recommended torque for M12 bolts is 40-43N·m

Figure. 4

5.1.3

According to the engineering drawing, place different length Rectangular Tube 100*90 and T Base 200/280 by 
below steps, as shown in Figure 6. 

Figure. 5

 Place the Rectangular Tube L1 horizontally to align with the hole of H Joint 240 near the end of 

girder , place bushing in one hand and put on bolts M16*130 in the other hand, then put on flat 
washers, spring washers, nuts and lock manually.

② 

Laying down the Rectangular Tube L2, and follow step

 to complete the other hole installation 

of H Joint 240.

Summary of Contents for PV-ezRack ezShade 2.0

Page 1: ...PV ezRack ezShade 2 0 Installation Guide V1 0...

Page 2: ...ate occupational health and safety regulations Please also pay attention to other relevant regulations in your local region Please check that you are using the latest version of the installation manua...

Page 3: ...ng to the figure above applying PV module 1960x992x35mm tilt angle 5 degree The MAX height from the ground is 2572mm The specific installation steps are as follows Planning 3 1 Installation Tools 3 To...

Page 4: ...Clamp R SDII 168 Rail 168 HJ SDII 158 240 H Joint 240 RR GU SDII 22 Rubber ring for Gutter 22 SP SDII R 168 Splice for Rail 168 BA SDII 200 Corrugated T Base 200 G SDII 150 4300 Girder 150 4300 BA SDI...

Page 5: ...the threads 4 2 2 General installation instructions Apply force to fasteners in the direction of thread Apply force uniformly to maintain required torque Professional tools and tool belts are recomme...

Page 6: ...1 Note The M20 bolts and matching nuts washers and spring washers are provided by installer As shown in Figure 3 place bolts M12 35 into H Joint 130 240 5 1 1 5 1 2 Figure 3 Figure 2 Installation Ins...

Page 7: ...n bolts M16 150 bushings flat washers spring washers and lock manually Keep the Tube L1 flat install the other hole with Corrugated T Base 200 Laying down the support rotate Tube L2 and Tube L3 align...

Page 8: ...nts if there is deviation The adjustment range of the slot hole of T Base as shown in Figure 10 Fasten all bolts after adjustment Recommended torque for M16 bolts is 100 105 N m M20 is 200 220 N m Fig...

Page 9: ...shown in Figure 16 5 3 Rail 60 Installation Figure 15 Figure 16 5 3 2 According to engineering drawings repeat the above operations to install the other Water Guide Rail 60 as shown in Figure 17 Note...

Page 10: ...hown in Figure 19 Figure 19 Installation Instruction Note Make sure each row of PV Module is without gap PV Modules are attached closely with the Rails and the ends of PV Module are aligned Then faste...

Page 11: ...8 bolts is 12 15N m 5 5 3 Tilt the Gutter and place it between the bottom of the PV Module and the Water Guide Rail60 as shown in Figure 24 The order of the Gutter is the same as the PV Module from lo...

Page 12: ...cho Yokohama 231 0023 Japan Tel 81 45 228 8226 Fax 81 45 228 8316 E mail sales clenergy co jp www clenergy jp Clenergy Philippines 145 Yakal St San Antonio village Makati City Philippines Tel 63 977 8...

Reviews: