Section 3 — Commissioning
Part No. 750-375
3-3
B. BOILER CONFIGURATION
On the Configuration Screen (#2) of the boiler panel make selections as follows (refer to the Hawk controls
manual for configuration help).
In order for the boiler to be in lead/lag sequence, the boiler has to be in “Rem/LLag” mode. This selection has
to be made on the firing rate screen of the boiler panel.
Note:
These settings are
made at the boiler control
panel, not at the Master
Panel.
Rem/Llag
Note:
This setting is made
at the boiler control panel,
not at the Master Panel.
Summary of Contents for Master Panel 8
Page 1: ...750 375 10 16 Master Panel 8 Eight Boiler Lead Lag Control Operation Manual...
Page 4: ......
Page 6: ......
Page 7: ...www cleaverbrooks com Section 1 Overview A Features 1 2 B Components 1 2 C Specifications 1 4...
Page 55: ...www cleaverbrooks com Section 5 Parts Master Panel 8 Parts List 5 3...
Page 56: ...Section 5 Parts Master Panel 8 5 2 Part No 750 375...
Page 58: ...Section 5 Parts Master Panel 8 5 4 Part No 750 375...
Page 60: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com...