Burner Operation and Control
2-6
750-211 (revised 2009)
Promethean Boilers, Model 4WI Manual
2.5 — Controls for Gas Firing
Depending upon the requirements of the insurance carrier or other governing agencies, the gas flow control sys-
tem, or gas train, may consist of some, or all, of the following items. Refer to the Dimension Diagram (DD) pre-
pared by Cleaver-Brooks for the installation.
FIGURE 2-6.
Pilot Gas Train and Main Gas Train
Component/Control
Description
1. Gas Pilot Valve
A solenoid valve that opens during the ignition period to admit fuel to the pilot. It
closes after main flame is established. The sequence of energizing and de-energizing
is controlled by the programming relay. A second gas pilot valve may be required by
insurance regulations.
2. Gas Pilot Vent Valve
When a second gas pilot valve is required, a normally open vent valve (optional
equipment) is installed between them. Its purpose is to vent gas to the atmosphere,
should any be present in the pilot line when the pilot valves are closed. The valve
closes when the pilot valves are energized.
3. Gas Pilot Shutoff Cock
For manually opening or closing the gas supply to the gas pilot valve.
4. Gas Pressure Gauge
Indicates gas pressure to pilot.
5. Gas Pressure Regulating
Valve
Reduces incoming gas pressure to suit the pilot.
6. Main Gas Valves
Electrically actuated shutoff valves that open simultaneously to admit gas to the
burner. The downstream valve is equipped with a “proof of closure” switch that is
connected into the pre-ignition interlock circuit.
7. Main Gas Cock
For manually opening and closing the main fuel gas supply downstream of the main
gas line pressure regulator. A second shutoff cock, downstream of the main gas
valve(s), is installed to provide a means of shutting off the gas line whenever a test is
made for leakage across the main gas valve.
Summary of Contents for 4WI
Page 46: ...Burner Operation and Control 2 22 750 211 revised 2009 Promethean Boilers Model 4WI Manual...
Page 62: ...Waterside Care and Requirements 3 16 750 211 revised 2009 Promethean Boilers Model 4WI Manual...
Page 70: ...Sequence of Operation 4 8 750 211 revised 2009 Promethean Boilers Model 4WI Manual...
Page 114: ...Adjustment Procedures 6 28 750 211 revised 2009 Promethean Boilers Model 4WI Manual...