Revision date: 06.19.12
Frame length of your building may differ
from what is shown.
Ground Level
Do not install any screws
into this purlin until the lower
panel is installed.
Maximum length extending
beyond purlin is 6".
Installed Ridge Cap
106478
Once the first set of roof panels is secured, install the
12.
next set of roof panels.
ATTENTION:
These panels
overlap the inside edge of
the installed panels by one (1) rib
and
must be square
on the purlin
. Verify that the lower end of the panel is
aligned with the end of the adjacent panel.
Install the horizontal closure strip (104709) between the
panel and purlins and continue as previously described.
Install the strip from inside the greenhouse for easier
access and to align it with the purlin.
Continue installing the corrugated polycarbonate roof
13.
panels and ridge cap (106478). Remember to secure
the overlap seams for all installed panels. If the length
and overlap dimensions were correct, cut all remaining
upper panels to 128".
NOTE:
If the final roof panel is too wide and extends
beyond the end rafter, trim the panel to the correct width
or
overlap the previous panel as needed
.
With the roof panels attached, continue with the
14.
installation of the lower roof panels.
INSTALL THE UPPER ROOF PANELS (continued)
Install Corrugated Panels
Overlap panels by one (1) rib as shown above.
Corrugated Panel
Rib
Corrugated Panel
Overlap adjacent
panel and slide
under the lip of the
corrugated ridge cap.