CLEARSPAN
™
PONY WALL BUILDINGS
18
108467_68_69_70
Revision date: 11.28.17
Ropes
Cover
Conduit
WARNING:
To prevent damage
and injury, do not leave the cover
unattended if it has not been
properly secured.
Frame length of your building may
differ from what is shown.
9
WARNING:
To prevent damage to the
cover and to prevent serious personal
injury, DO NOT attempt to install the
main cover on windy days.
NOTE:
Use lifts and additional assistants (if needed) to help pull the cover up and over the frame.
5. Once the main cover is pulled into position, center the cover on the frame (end-to-end and side-to-side).
6. Tie the ropes, used to pull the cover into position, to the frame to temporarily hold the cover in place.
PULL MAIN COVER OVER FRAME
Gather the parts:
• Main cover (with conduits inserted)
• Ropes (provided by customer) or strap long enough to reach over the frame
• Box cutter or utility knife
WARNING:
To prevent damage and injury, do not leave the cover unattended if it has not been properly
secured.
Use ropes or straps to keep the cover from blowing off the frame during installation.
Main Cover Procedure (describes the installation of a single cover)
1. Attach ropes or straps to both ends of the cover conduit positioned
farthest from the frame
if the cover
was spread out on the ground. Space additional ropes every 20' or so to prevent cover damage when
pulling onto the frame. Cut small slits in the pocket to gain access to the cover conduit.
ATTENTION:
If the cover is fan folded, as shown in the diagram on previous page, tie the rope or straps
to the conduit that is on the top of the folded cover.
2. Cut 4 or 5 pieces of 2" strap (13'-14' long) from the bulk roll. Evenly space the straps and wrap each
around the remaining cover conduit. Insert the free ends of each strap into a ratchet attached to the side
wall and slightly tighten to keep the strap in place. These straps keep the free end of the cover in place
as the other end is pulled up and over the frame.
3. With all ropes attached to the cover conduit, lift and carry the conduit and cover toward the base of the
assembled frame.
This is the conduit that will be pulled over the frame to the other side.
4. Toss the ropes over the frame and pull the cover into position. Position 2-3 assistants at each rope.
Verify that the cover pockets are to the inside of the building. This will be the underside of the cover
when it is pulled into position on the frame.