CLEARSPAN™ CANOPIES

10

Revision date: 07.21.08

INSTALL MAIN FRAME LEGS

Take the remaining 131P088 (88" plain) pipes and 

1. 

insert them into the 3-way and 4-way couplers of the 

main frame. 

Do not install the main frame legs during a 

storm or windy day

HELPFUL HINT:

 It's best to install the legs along one 

side of the main frame and then install them on the 

remaining side.
Secure each pipe in a 3-way and 4-way coupler using 

2. 

the locking eyebolt. If the couplers are not equipped 

with locking eyebolts, secure each pipe in the coupler 

using a Tek screw. 

Position Tek screws so they will not 

touch the main cover or end panels when these are 

installed

.

After all legs are installed, consult the 

3. 

Must Read 

document for the instructions that describe how to 

install the anchor kit assemblies (#103599) and install 

two anchors in the locations shown below.

This side roof cover 

can hang down or can 

be folded onto the main 

cover during the frame 

leg installation.

Plain Pipe 

(#131P088)

With two (2) corners of the main frame anchored to the 

4. 

site, square the frame and install the side roof cover 

supports and anchors. 

ATTENTION:

 Tighten 

the anchors until snug. 

DO NOT over tighten.

Anchors ware tightened 

completely after all 

anchors are installed.

Install two (2) anchors 

at each corner 

indicated by arrows.

SQUARE THE ASSEMBLED FRAME

With the frame in position, perform a final square of 

1. 

the frame by measuring diagonally (corner to corner) 

at the bottom of the legs and verify that the two 

measurements are equal. Adjust if needed.
Adjust width. Measure width from center of rafter leg to 

2. 

center of other rafter leg of the 

same rafter assembly

Adjust if needed.

Examine the frame and remove any sharp edges from 

3. 

the frame or reposition screws so they do not come in 

contact with the roof covers.
Verify that the screws used to secure the purlin pipe 

4. 

joints are tight and positioned so they do not touch the 

covers. 

 

NOTE:

 These purlin joints and Tek screws can be 

taped to protect the cover if desired.
After the frame is squared, read or reread the 

5. 

MUST 

READ

 document and continue with the assembly and 

anchoring of the shelter. 

 

NOTE:

 The side roof legs are aligned with the legs of 

the main frame assembly when installed correctly. 

Frame shown may differ in length, used for illustration 

purposes.

Summary of Contents for 105706

Page 1: ... 07 21 08 2008 ClearSpan All Rights Reserved Reproduction is prohibited without permission ClearSpan Party Tent 17 Wide Photo may show a different but similar model STK DIMENSIONS 105706 17 W x 20 L 105707 17 W x 30 L 105708 17 W x 40 L ...

Page 2: ...rranty and may cause serious injury and damage LOCATION Choosing the proper location is an important step before you begin to assemble the structure The following suggestions and precautions will help you determine whether your selected location is the best location Never erect the structure under power lines Identify whether underground cables and pipes are present before preparing the site or an...

Page 3: ...in the assembly read through the following definitions before you begin to assemble your shelter Conduit An assembly of pipes used to secure the main cover and end panels if equipped Purlins and some strut assemblies also consist of connected pipes to form a conduit Each pipe joint of a conduit assembly is secured with a self tapping Tek screw Coupler or Fitting A part of the frame assembly where ...

Page 4: ...n easily inventory the parts Refer to the Bill of Materials Spec Sheets Verify that all parts listed on the Bill of Materials Spec 2 Sheets are present If anything is missing or you have questions consult the Pictorial Parts Guide and all shelter diagrams for clarification or contact Customer Service NOTE At this time you do not need to open the plastic bags containing smaller parts such as fasten...

Page 5: ...s and photos will help you identify the different parts and show you how they are used Not all parts are shown 102191 3 Way Coupler 102192 4 Way Coupler FA4482B Tek screw CC4595 Tie Down 8 Snugger Ball 105575 Star Nut FAMF03B Fender Washer FALB02B Nut FA2071 Eyebolt ...

Page 6: ...l injury and damage to the shelter fasten and tighten a Tek screw at each pipe and coupler joint To prevent cover damage install the Tek screw so that it does not touch the main cover or any optional side or end panels once these are installed 4 Way Coupler no lock bolt 4 Way Coupler includes lock bolt Additional Parts Identification Notes In some instances there can be differences between the par...

Page 7: ... coupler using the locking 2 eyebolt If the couplers are not equipped with locking eyebolts secure each pipe in the coupler using a Tek screw Secure each purlin pipe joint with a Tek screw and then 3 tape the screw to protect the cover when it is installed ATTENTION Position Tek screws so they will not touch the main covers or side panels if equipped when these are installed Pipe Identification As...

Page 8: ...bove insert Use one snugger ball for each grommet Once the main cover is installed unfold the side roof 3 cover along the frame and attach it to the main roof frame using the snugger balls The dashed line in the diagram below shows where to attach the side roof cover After the covers are attached assemble the side roof 4 supports and install the main frame legs WARNING To prevent property damage a...

Page 9: ...88 and install one 1 star nut 105575 in one end of the pipe Use a hammer to tap 1 the star washer into the pipe opening Do not use a tool that can damage the threads in the center of the star nut Locate the eyebolts fender washers and nuts and assemble each as shown below 2 FA2071 Eyebolt FAMF03B Fender Washer FALB02B Nut 105575 NOTE The remaining nuts and washers are used when the eyebolt assembl...

Page 10: ...the frame and install the side roof cover supports and anchors ATTENTION Tighten the anchors until snug DO NOT over tighten Anchors ware tightened completely after all anchors are installed Install two 2 anchors at each corner indicated by arrows SQUARE THE ASSEMBLED FRAME With the frame in position perform a final square of 1 the frame by measuring diagonally corner to corner at the bottom of the...

Page 11: ...r Eyebolt Fender Washer Nut Fender Washer Nut Repeat Step 1 and attach all remaining eyebolt 2 assemblies to the side roof cover Take one 1 plain pipe leg 100P088 for the side 3 roof cover and twist it onto one of the attached corner eyebolts Cover shown may differ slightly from the actual cover Pipe with installed star nut NOTE Hand tighten the pipe until it is snug The nuts should be tight to ke...

Page 12: ...lly checked to ensure that your shelter is maintained properly Regularly check the roof covers to see that they remain tight and in proper repair Check connections and all fasteners to verify that they remain tight Do not climb or stand on the shelter at anytime Remove debris and objects that can accumulate on the shelter Use tools that will not damage the cover when removing debris Remove snow to...

Page 13: ...LEARSPAN CANOPIES Revision date 07 21 08 Quick Start Guide 17 Wide Party Tent 105706 17 x 20 105707 17 x 30 10 On Center Rafter Spacing 10 On Center Rafter Spacing 105708 17 x 40 10 On Center Rafter Spacing ...

Page 14: ...CLEARSPAN CANOPIES 14 Revision date 07 21 08 FRONT PROFILE ...

Page 15: ...15 CLEARSPAN CANOPIES Revision date 07 21 08 SIDE PROFILE 105706 10 0 Rafter Spacing 20 0 Length 131S052 Pipe 131P068 Pipe ...

Page 16: ...CLEARSPAN CANOPIES 16 Revision date 07 21 08 SIDE PROFILE 105707 Spacing 10 0 Rafter 30 0 Length 131S052 Pipe 131P068 Pipe ...

Page 17: ...17 CLEARSPAN CANOPIES Revision date 07 21 08 SIDE PROFILE 105708 Length 40 0 Rafter Spacing 10 0 131S052 Pipe 131P068 Pipe ...

Page 18: ...CLEARSPAN CANOPIES 18 Revision date 07 21 08 CONNECTIONS ...

Page 19: ...19 CLEARSPAN CANOPIES Revision date 07 21 08 CONNECTION DETAILS ...

Reviews: