15
CLEARSPAN
™
JUBILEE TENTS
Revision date: 05.19.09
4. After installing and securing the corner legs, install and
secure the remaining legs.
6. Slide each fitting up the leg and position it 8" to 9" from
the corner or side coupler (
center-to-center
) as shown
in the pictures below. Secure with 5/16" hex key. Set
screws are loosened and retightened when pipes are
added.
Leg and Lower Base Assembly
The following steps will require the assistance of several
people, or a machine designed for lifting. Heavy lifting
is involved. Height assistance may also be required. If
needed, use ladders and/or steady platforms to safely
elevate the frame.
1. Gather the ten (10) sections of #190P094D pipe for the
legs
.
2. Starting at two corners, carefully hoist the roof section
of the frame high enough to slide leg pipes, holes first,
into the corner couplers. Align the holes and secure
with a carriage bolt and nut.
Support the frame between
the corners with a temporary brace if needed.
3. Move to the opposite side and repeat the step to install
the leg pipes in those corners.
Actual frame may differ from frame shown
Actual frame may differ from frame shown
8" - 9"
8" - 9"
FRAME ASSEMBLY (continued)
5. With all legs installed, lift each leg pipe and slip the
appropriate short cross or 3-way open corner onto the
leg pipe. See the diagram that follows for details.