12
Revision date: 09.16.09
FINAL FRAME INSPECTION FOR
COVER INSTALLATION
Before the cover is installed, complete
these steps to prepare the frame for
cover installation.
1. Verify that all fasteners are installed
and tight.
2. Inspect the frame for fasteners
that are installed in areas where
the main cover meets the frame.
Reposition these fasteners (if
possible) or wrap with tarp or duct
tape to protect the cover.
3. Inspect all pipe and connections for
sharp edges and file smooth and/or
wrap with duct tape.
5
SIDE STRUT INSTALLATION
Complete these steps to install the four (4) side struts:
1. Locate one strut and position it between one first interior rafter leg and the leg of the second interior
rafter as shown below.
2. Attach one end of the strut to the previously installed band clamp as shown in the diagram below.
NOTE:
Head of bolt on the band clamp must face the outside.
3. Attach the remaining end of the strut to the baseboard using a customer-supplied wood screw. See
the diagram below for location.
NOTE:
A baseboard provides a place to attach each strut and helps keep the ground posts at the
required depth. The customer is responsible for providing a baseboard for this frame.
If no baseboard is used, pre-drill mounting hole in ground post, reposition strut and attach using a
customer-supplied fastener.
4. Repeat the above steps to attach the remaining side struts to the shelter.
5. After securing the struts, verify that all clamps are secured with a Tek screw to the rafters.
End
Rafter
Ground Level
Baseboard
Baseboard is required to
secure strut as shown.
Strut
Interior
Rafter
Strut
End Rafter
Band
Clamp
Photo shows the strut
attached to the inside of
the customer- supplied
baseboard.
Attach strut to baseboard
using customer-supplied
wood screw.
Struts