Place the isolation pad in position over the predrilled holes and align as necessary. Lift the frame onto the isolation
pad and line up with holes.
Ensure that the anchor’s expansion shield is not expanded. Place the end of the anchor into the predrilled hole.
Repeat for the other drilled holes. Make sure the anchor is fully embedded in the concrete.
Align the edges of the 2” square washer parallel with the slots in the frame base to obtain the maximum material
overlap. Once aligned, tap each anchor/washer assembly until it is seated firmly in the hole against the 2” square
washer.
Pre-tighten each anchor with a socket wrench or box-end wrench; do not use an open-end wrench (which could easily
slip off and cause injury). Before final tightening, ensure that the frame is properly aligned (in the row and with any
adjacent frames). Torque each anchor to 60 ft-lbs.
Note:
When using the break-off type anchor, a torque wrench is not required. The anchor’s (red) torque cap shears off
at a predetermined torque value (approximately 60 ft-lbs.), leaving a green seal on the bolt head, indicating proper
tightening.
The anchoring line up should look like this:
Note:
Square
washers will be
packaged in base
of frames
Threaded Rod
4.
5.
6.
7.
8.