2-3
Cisco UCS C3160 Rack Server Installation and Service Guide
OL-32062-01
Chapter 2 Installing the Server
Preparing for Server Installation
Warning
This product relies on the building’s installation for short-circuit (overcurrent) protection. Ensure that
the protective device is rated not greater than: 250 V, 15 A.
Statement 1005
Warning
Installation of the equipment must comply with local and national electrical codes.
Statement 1074
When you are installing a server, use the following guidelines:
•
Plan your site configuration and prepare the site before installing the server. See the
Cisco UCS Site
Preparation Guide
for the recommended site planning tasks.
•
Ensure that there is adequate space around the server to allow for servicing the server and for
adequate airflow. The airflow in this server is from front to back.
•
Ensure that the air-conditioning meets the thermal requirements listed in the
Server Specifications,
page A-1
.
•
Ensure that the cabinet or rack meets the requirements listed in the
Rack Requirements, page 2-4
.
•
Ensure that the site power meets the power requirements listed in the
Server Specifications,
page A-1
. If available, you can use an uninterruptible power supply (UPS) to protect against power
failures.
Summary of Contents for UCS C3160
Page 6: ...Contents vi Cisco UCS C3160 Rack Server Installation and Service Guide OL 32062 01 ...
Page 10: ...x Cisco UCS C3160 Rack Server Installation and Service Guide OL 32062 01 ...
Page 12: ...xii Cisco UCS C3160 Rack Server Installation and Service Guide OL 32062 01 ...
Page 13: ...xiii Cisco UCS C3160 Rack Server Installation and Service Guide OL 32062 01 ...