2.2 Work Items, Work Assignment, and Work Time
“Table 2.2” lists the work items, standard work time, and the person in charge of these types of work.
Table 2.2
Work item
Person in charge
Work time
(minute)
Checking the delivered items
Service engineer
5
Installing option
Service engineer
30
Verifying operation
Service engineer
5
Preparation of handing over to
the system administrator
Service engineer
1
Handover to the system administrator
System administrator and
Service engineer
5
SET0203000
2.3 Procedure for installing a system board
SET0203010
2.3.1 Checking the delivered items
(1) Check the delivered items by confirming the following.
1. The types and quantities of delivered options match those written on the order sheet.
2. The delivered items match those listed in the List of Accessories.
3. All cabinets are free of any abnormalities such as scratches, dents, or dirt.
4. The specifications and version level of units delivered separately due to delivery considerations
are available for the target functions.
(2) Proceed to “
SET0203020
2.3.2 Installing option
Install according to the following procedures.
ANNT)
- The installation location and quantity have to indicate by the system administrator.
- Confirm connecting position of power cable of the Base Unit beforehand.
(1) Turn off AC power of the Base Unit.
(2) Remove the system board dummy.
(3) Install the system board.
(4) Turn on AC power of the Base Unit.
→ Wait about a minute until green indicator of t
he “System Power” is turned off.
(5) Make sure that the Alarm indicator of the system board is not lit. (See “Figure 2.3.2”.)
Summary of Contents for C880 M5
Page 94: ...94 Appendix ...
Page 97: ...97 Figure B 1 Distribution panel breaker characteristics ...
Page 102: ...102 Figure D 3 3 When 1 AC Source Figure D 3 4 When 1 AC Source ...
Page 105: ...105 Figure E 2 1 2 ...
Page 108: ...108 Figure E 3 1 2 ...
Page 112: ...112 Figure E 5 1 2 ...
Page 119: ...119 Figure E 10 2 ...
Page 135: ...135 Figure F 7 1 5 ...
Page 137: ...137 Figure F 8 1 2 Figure F 8 1 3 ...
Page 142: ...142 Figure F 9 3 3 Figure F 9 3 4 ...
Page 144: ...144 Figure F 10 1 3 ...
Page 152: ...152 Figure F 13 1 1 Module MC 0JXEL1 Figure F 13 1 2 Module MC 0JCEK1 ...
Page 156: ...156 APP0614000 F 14 Installing M 2 Flash Device See Figure F 14 Figure F 14 ...
Page 163: ...163 APP0617000 F 17 Installing TPM See Figure F 17 Figure F 17 ...
Page 165: ...165 Figure G 1 2 ...
Page 171: ...171 APP0902000 I 2 Fibre Channel card Figure I 2 ...
Page 172: ...172 APP0903000 I 3 SAS card SAS RAID controller card Figure I 3 ...
Page 173: ...173 APP0904000 I 4 CNA card Figure I 4 ...
Page 174: ...174 APP0905000 I 5 Infiniband HCA card Figure I 5 ...