Fitting the Visual 180 ° or Visual 360 ° return/discharge panel:
We recommend fitting this component only when the box is already installed in the suspended ceiling to prevent
damage to the panel or clogging of the filter during tests when switching on for the first time.
■ Remove the electrostatic film applied to the box's air intake.
■ Open and remove the intake grille on the nozzle (Fig. 5, a).
■ Fit the panel (Fig. 5, b). Warning: for improved efficiency, direct the Visual 180° nozzle towards the glass walls.
■ Pivot the 4 bolts to hold the nozzle in position (Fig. 5, c).
■ Tighten the 4 bolts (Fig. 5, d).
■ Refit and close the intake grille again.
Do not press hard on the corners of the panel as this could deform them. Check that the panel is
securely affixed.
The
COADIS LINE™
has a directly integrated return/discharge interface which is able to isolate the flow of air
handled by the unit from the suspended ceiling. The use of a connecting air duct between the air return and discharge
is therefore not necessary.
The
COADIS LINE™
has an inlet for clean fresh air equipped with a 100 mm diameter connection sleeve integrated
in the frame, with a removable plug (Fig. 6 - a). Recommended max fresh air flow 90 m
3
/h.
When using the
COADIS LINE™
with fresh air, as a filtration cassette according to standard VDI 6022, the air
handling unit must fulfil the criteria for this standard and must be equipped with an F7 filter as a minimum.
The ducts used may be coated with an anti-condensation material. (Fibreglass 12-25 mm thick)
■ Remove the plug from the fresh air inlet.
■ Position the duct on the connection sleeve.
■ Place a retaining clamp around the duct in contact with the connection sleeve.
■ Tighten the clamp and check the integrity of the connection.
To protect itself effects of condensation (no open valve when the ventilation is cut).
4.3 - Hydraulic connections
Water always flows into the bottom of the coil and exits at the top.
The pipes are positioned in the suspended ceiling as shown in Fig. 7.
The coils are equipped with a header coupling with flat face swivel nuts with a female thread, diameter G½˝ and
an O-ring. (Supplied by
CIAT
) .
The header coupling is equipped with an air bleed valve (Fig. 8 - a) at the high point with partial draining at the low
points (Fig. 8 - b) that can be manoeuvred using a 7 mm Allen key or a flat-blade screwdriver.
Recommendations for venting or draining the unit
Before carrying out work on the unit, check that the power supply is cut off and locked.
Only experienced, qualified technicians may perform installation and maintenance work on the machine. They must
be provided with personal protective equipment (PPE).
The technician must take all the necessary precautions to recover the water drained during venting or draining
procedures.
4 - INSTALLATION AND CONNECTIONS
COADIS LINE
TM
600
EN-18
Summary of Contents for COADIS LINE 600
Page 1: ...COADIS LINE TM 600 05 2022 EN7521261 02 Instruction manual...
Page 2: ...35kg 50 C 10 C COADIS LINETM 600 II...
Page 3: ...Fig 1 g h k b j d j e c f a III COADIS LINETM 600...
Page 5: ...Fig 4 Recommended Visual 360 Visual 180 Pr conis 600mm 300 mini a b V COADIS LINETM 600...
Page 6: ...Fig 5 45 a c d b COADIS LINETM 600 VI...
Page 7: ...Fig 6 Fig 7 Fig 8 a a b 131 5 202 67 5 157 40 S1 S E E1 60 18 5 VII COADIS LINETM 600...
Page 10: ...Fig 13 Fig 14 a a b Fig 15 a Fig 16 a b Fig 17 COADIS LINETM 600 X...
Page 11: ...Fig 18 a b c d e f g XI COADIS LINETM 600...
Page 12: ...Fig 19 a b Fig 20 a b Fig 21 COADIS LINETM 600 XII...
Page 31: ......