Exterior side pads with two holes
Interior pads with four holes
1. If the tiles are being mounted on an external support structure, ensure the external support
structure is anchored to the wall and/or to the floor.
The design and anchoring of the LED display structure is not the responsibility of Christie
Digital Systems USA Inc. Contact a Christie representative for structure design options.
2. Determine where the mounting pads should be installed.
a) Find the center of the bottom of the display area.
b) Position the mounting template with the bottom left template hole centered on the point
identified in step 2a.
c) Level and hang the mounting template on the support structure.
3. Insert the springs into the mounting pads.
4. Install the mounting pads.
a) Place the mounting pads inside the template holes, and secure them to the support
structure.
For installation onto a steel structure, tighten the M6 screws to a torque of 3.55 Nm
(31.42 lbs.in).
For installation onto a wooden surface:
•
M8 wood screws—Tighten to a torque of 11.5 Nm (101.8 lbs.in)
Installation and setup
Velvet LED Display System Installation and Setup Guide–CorePlus Series (Remote Power)
20
020-102423-01 Rev. 1 (06-2018)