Stirrer Shaft and Agitator Assembly 

 

 
 
 
 
 
 

 
 
 

 
 

 
 
 

 

 

The stirrer shaft and agitators are assembled and installed when shipped. Use the following 

instructions should you need to remove or adjust these components. 

 

Components Needed for Stirrer Shaft and Agitator Assembly: 

1ea  CG-2097  Stirrer Shaft 

1ea  CG-2093  Flake Retaining Cup 

1ea  CG-2095  Upper PTFE Agitator 

1ea  CG-2096  Lower High Viscosity PTFE Agitator 

 

1.

 

The lower agitator assembly (CG-2096) is placed on the end of the stirrer shaft aligning the 

hole on the stirrer shaft with the holes in the PTFE hub. The sand blasted portion is the lower end 

of the stirrer shaft. Insert the glass filled PTFE pin. The pin must be cut to 24mm long before 

installing. Tighten the compression fitting. PLEASE NOTE: THE PTFE PIN MUST BE INSTALLED BEFORE 

USING. 

2.

 

The upper agitator assembly (CG-2095) slides over the end of the shaft. The height from the 

bottom will depend on the total volume you intend to run in the reactor. 

3.

 

Once you have the upper agitator in place, tighten the compression fitting as tight as possible 

(by hand). For use at higher temperatures, Chemglass recommends heating the upper 

agitator hub with a heat gun and then retightening. Then tighten the set screw on the flat of 

the stirrer shaft using a screwdriver. This will minimize the possibility of the agitator falling or 

slipping at higher temperatures.  

4.

 

The PTFE flake retaining cup (CG-2093) slides over the top of the stirrer shaft and is positioned 

approximately 18 inches from the bottom of the lower agitator assembly (CG-2096). For the 

cup to work effectively, the final position will have to be adjusted so that it is not less than 1 

inch away from the bottom of the PTFE stirrer bearing. 

 

CG-2095 

Upper Agitator 

CG-2096 

Lower Agitator 

CG-2097 

Stirrer Shaft 

Hole through the 

Lower Portion of the 

Stirrer Shaft 

Glass Filled PTFE Pin 

(MUST BE CUT TO 

LENGTH BEFORE 

INSTALLING) 

Summary of Contents for CG-1959-U1000

Page 1: ...8360 Phone 800 843 1794 Fax 800 922 4361 ASSEMBLY INSTRUCTIONS FOR UNJACKETED BENCHTOP FILTER REACTOR SYSTEMS Support Frame with Oversized Rugged S S Uprights and Heavy Duty PTFE Coated Aluminum Fitti...

Page 2: ...om the wood crates in case you need to return items for repair or replacement Crate 1 Unpack the support frame with reactor and components by removing the plastic electrical ties that hold the reactor...

Page 3: ...0 Small Kwik Klamp II 1ea CG 3498 03 90 Support Rod 1 The support frame has a universal motor mount It can be used with an vertical or horizontal electric air or optional explosion proof XP motor The...

Page 4: ...embly CG 2095 slides over the end of the shaft The height from the bottom will depend on the total volume you intend to run in the reactor 3 Once you have the upper agitator in place tighten the compr...

Page 5: ...it is pushed down on all edges evenly 5 Wrap the lower outlet adapters with NPT end with PTFE tape Thread the adapter into the filter base until it becomes snug DO NOT OVER TIGHTEN 6 Attach the beade...

Page 6: ...vessel lid onto the vessel carefully insert the end of the stirrer shaft through the 45 50 center neck of the lid PLEASE NOTE THE MECHANICAL SEAL STIRRER BEARING IS NOT INSERTED IN THE HEAD AT THIS TI...

Page 7: ...www cglifesciences com technical service cglifesciences com...

Page 8: ...www cglifesciences com technical service cglifesciences com...

Page 9: ...uch as 20 mA or 10 V Zener barriers contain intrinsically safe circuits that are to be used to drive intrinsically safe field devices with hazardous area The manufacturer s data sheets must be consult...

Reviews: