BAYARD
10 BFEPV
&
13 BFEPV
OPERATION
THE OPERATION OF THIS APPLIANCE IS THE SAME AS THAT FOR THE BAYARD
10 CFPV & 13 CFPV. FOR INFORMATION, REFER TO PAGE 2 OF THIS SECTION.
MAINTENANCE
ENSURE THE APPLIANCE IS ELECTRICALLY SAFE ALL TIMES
FRONT CASE REMOVAL
1. Pull off the control knobs.
2. Unscrew the three retention screws (above
the water flow control and top and bottom
of the unit).
3. Pull the case forward and off.
NOTE: This is a sealed case therefore when
replacing the case, ensure that the unit is air
tight.
BALANCED FLUE TERMINAL REMOVAL
The flue terminal can be removed from the front
case by unscrewing the four retention screws,
Fig.1.
BALANCED FLUE(Fig 1)
GAS VALVE AND WATER SECTION, REMOVAL.
1. Turn off the gas and water supplies.
2. Remove the front case and drain
the
unit.
3 Unscrew the pilot supply pipe retention
bracket and remove pipe and bracket.
4 Unscrew the burner manifold retention
screws and lift off the manifold.
5 Remove the scre
.
ws which retain the gas
section to the rear case.
6 Disconnect the four water connections from
the water section.
7 Disconnect the gas supply connection.
8 Ease the complete assembly downwards and
lift away.
Page 10
1.
Flue exhaust
2.
Heat exchanger
3.
Sealing gasket
4
Main burner
5.
Gas control
6.
Gas section
7.
Water flow control
8.
Water section
9.
Piezo assembly
10.
Water regulator
I
drain
MAIN
COMPONENTS (Fig.2)