29
FIELD POWER SUPPLY
If equipped with optional powered convenience outlet: the power
source leads to the convenience outlet’s transformer primary are
not factory connected. Installer must connect these leads accord
-
ing to required operation of the convenience outlet. If an always-
energized convenience outlet operation is desired, connect the
source leads to the line side of the unit-mounted disconnect.
(Check with local codes to ensure this method is acceptable in
your area.) If a de-energize via unit disconnect switch operation of
the convenience outlet is desired, connect the source leads to the
load side of the unit disconnect. On a unit without a unit-mounted
disconnect or HACR, connect the source leads to the terminal
block with unit field power leads. See Fig. 40.
Fig. 40 —
Location of TB1
Field power wires are connected to the unit at line-side pressure
lugs on the terminal block (see wiring diagram label for control
box component arrangement) or at factory-installed option non-
fused disconnect switch or HACR breaker. Use copper conductors
only. See Fig. 41.
Figure 42-48 are typical control and power wiring diagrams.
NOTE: Make field power connections directly to line connection
pressure lugs only.
Fig. 41 —
Disconnect Switch and Unit
LOAD
SIDE
SEE
DETAIL
A
DETAIL
A
LINE
SIDE
BLK
YEL
BLU
CONTROL BOX
L3
L2
L1
WARNING
FIRE HAZARD
Failure to follow this warning could result in personal injury,
death, or property damage.
Do not connect aluminum wire between disconnect switch and
unit. Use only copper wire.
COPPER
WIRE ONLY
ELECTRIC
DISCONNECT
SWITCH
ALUMINUM
WIRE
Summary of Contents for WeatherExpert 50LC14
Page 4: ...4 Fig 2 50LC Vertical Airflow Size 14...
Page 5: ...5 Fig 3 50LC Horizontal Airflow Size 14...
Page 6: ...6 Fig 4 50LC Back View and Condensate Drain Location Size 14...
Page 7: ...7 Fig 5 50LC Corner Weights and Clearances Size 14...
Page 8: ...8 Fig 6 50LC Bottom View Size 14...
Page 9: ...9 Fig 7 50LC Vertical Airflow Sizes 17 20...
Page 10: ...10 Fig 8 50LC Horizontal Airflow Sizes 17 20...
Page 11: ...11 Fig 9 50LC Back View and Condensate Drain Location Sizes 17 20...
Page 12: ...12 Fig 10 50LC Corner Weights and Clearances Sizes 17 20...
Page 13: ...13 Fig 11 50LC Bottom View Sizes 17 20...
Page 14: ...14 Fig 12 50LC Vertical Airflow Sizes 24 26...
Page 15: ...15 Fig 13 50LC Horizontal Airflow Sizes 24 26...
Page 16: ...16 Fig 14 50LC Back View and Condensate Drain Location Sizes 24 26...
Page 17: ...17 Fig 15 50LC Corner Weights and Clearances Sizes 24 26...
Page 18: ...18 Fig 16 50LC Bottom View Sizes 24 26...
Page 21: ...21 Fig 19 Roof Curb Details 14 Size Unit...
Page 22: ...22 Fig 20 Roof Curb Details 17 and 20 Size Units...
Page 23: ...23 Fig 21 Roof Curb Details 24 and 26 Size Units...
Page 30: ...30 Fig 42 50LC 14 26 Electro Mechanical Control Wiring Diagram...
Page 31: ...31 Fig 43 50LC 14 26 RTU Open Control Wiring Diagram...
Page 32: ...32 Fig 44 50LC 14 26 SystemVu Control Wiring Diagram...
Page 35: ...35 Fig 47 Typical Power Wiring Diagram SystemVu Controls 50LC Unit 208 230V Shown...
Page 36: ...36 Fig 48 Typical Power Wiring Diagram SystemVu Controls 50LC Unit 460V 575V Shown...
Page 80: ......
Page 81: ......