d. Remove bolts holding motor to blower housing and
slide motor out of wheel (40+/--10 in.--lb. when re-
assembling).
e. Remove blower wheel from housing.
f. Clean wheel and housing.
10. Reassemble motor and blower by reversing steps 9a,
through 9e. Be sure to reattach ground wire to the blower
housing.
11. Verify that blower wheel is centered in blower housing
and set screw contacts the flat portion of the motor shaft.
Loosen set screw on blower wheel and reposition if neces-
sary.
12. Spin the blower wheel by hand to verify that the wheel
does not rub on the housing.
13. Reinstall blower assembly in furnace.
14. Reinstall 2 screws securing blower assembly to blower
deck.
15. Reconnect blower leads to furnace control. Refer to fur-
nace wiring diagram, and connect thermostat leads if pre-
viously disconnected.
16. To check blower for proper rotation:
a. Turn on electrical supply.
ELECTRICAL SHOCK HAZARD
Failure to follow this warning could result in personal
injury, or death.
Blower access door switch opens 115--v power to furnace
control. No component operation can occur unless switch is
closed. Exercise caution to avoid electrical shock from
exposed electrical components when manually closing this
switch for service purposes.
!
WARNING
b. Manually close blower access door switch.
NOTE
: If R--W thermostat terminals are jumpered at the time
blower access door switch is closed, blower will run for 90 sec
before beginning a heating cycle.
c. Perform component self--test as shown at the bottom
of the SERVICE label, located on the front of blower
access door.
d. Verify blower is rotating in the correct direction
17. If furnace is operating properly, RELEASE BLOWER
ACCESS DOOR SWITCH. Remove any jumpers or re-
connect any disconnected thermostat leads. Replace blow-
er access door.
18. Downflow or horizontal furnaces with vent pipe through
furnace only:
a. Install and connect short piece of vent pipe inside fur-
nace to existing vent.
b. Connect vent connector to vent elbow.
19. Reinstall outer door.
20. Turn on gas supply and cycle furnace through one com-
plete heating and cooling cycle. Verify the furnace temper-
ature rise as shown in Adjustments Section. Adjust tem-
perature rise as shown in Adjustments Section. If outdoor
temperature is below 70
_
F, turn off circuit breaker to out-
door unit before running furnace in the cooling cycle.
Turn outdoor circuit breaker on after completing cooling
cycle.
Cleaning Heat Exchanger
The following steps should be performed by a qualified
service agency:
NOTE
: If the heat exchangers get a heavy accumulation of soot
and carbon, they should be replaced rather than trying to clean
them thoroughly. A build--up of soot and carbon indicates that a
problem exists which needs to be corrected, such as improper
adjustment of manifold pressure, insufficient or poor quality
combustion air, incorrect size or damaged manifold orifice(s),
improper gas, or a restricted heat exchanger. Action must be taken
to correct the problem.
A05025
Fig. 49 -- Igniter Position -- Side View
1-7/8
(47.6 mm)
A05026
Fig. 50 -- Igniter Position -- Top View
If it becomes necessary to clean the heat exchangers because of
dust or corrosion, proceed as follows:
1. Turn OFF gas and electrical power to furnace.
2. Remove outer access door.
3. Disconnect vent connector from furnace vent elbow.
4. For downflow or horizontal furnace having an internal
vent pipe, remove internal vent pipe within the casing.
5. Disconnect wires to the following components. Mark
wires to aid in reconnection (be careful when disconnect-
ing wires from switches because damage may occur):
a. Draft safeguard switch.
b. Inducer motor.
c. Pressure switches.
d. Limit overtemperature switch.
e. Gas valve.
f. Hot surface igniter.
g. Flame--sensing electrode.
h. Flame rollout switches.
6. Remove screws that fasten the collector box assembly to
the cell panel. Be careful not to damage the collector box.
Inducer assembly and elbow need not be removed from
collector box.
7. Disconnect gas line from gas manifold.
8. Remove the four screws that attach the burner assembly to
the cell panel. The gas valve and individual burners need
not be removed from support assembly. Remove NOx baf-
fles, if installed.
NOTE
: Be very careful when removing burner assembly to
avoid breaking igniter. See Fig. 49--50 for correct igniter location.
9. Using field--provided 25--caliber rifle cleaning brush,
36--in. (914 mm) long, 1/4--in. (6 mm) diameter steel
spring cable, a variable speed, follows: