Installation Instructions

Electric Heater Packages

NOTE

: Read the entire instruction manual before starting the

installation.

SAFETY CONSIDERATIONS

Installing and servicing of heating and air conditioning equipment

can be hazardous due to system pressures and electrical
components. Only trained personnel should install or service

heating and air conditioning equipment.
Untrained personnel can perform basic maintenance functions such
as cleaning coils, or cleaning and replacing filters. All other

operations should be performed by trained personnel. When
working on heating and air conditioning equipment, observe

precautions in literature, on tags, and on labels attached to the unit.
Follow all safety codes. Wear safety glasses and work gloves. Have
a fire extinguisher available.

Recognize safety information. This is the safety--alert symbol

.

When you see this symbol on the unit and in instructions or
manuals, be alert to the potential for personal injury.
Understand the signal words DANGER, WARNING, and
CAUTION. These words are used with the safety--alert symbol.

DANGER identifies the most serious hazards which

will

result in

severe personal injury or death. WARNING signifies hazards
which

could

result in personal injury or death. CAUTION is used

to identify unsafe practices, which

may

result in minor personal

injury or product and property damage. NOTE is used to highlight

suggestions which

will

result in enhanced installation, reliability, or

operation.

ELECTRICAL SHOCK HAZARD

Failure to follow this warning could result in personal injury

or death.
Before installing, modifying or servicing system, always turn

off main power to system. There may be more than one

disconnect switch. Lock out and tag switch with a suitable

warning label.

!

WARNING

PERSONAL INJURY HAZARD

Failure to follow this caution may result in personal injury.
Sheet metal parts may have sharp edges or burrs. Use care and

wear appropriate protective clothing and gloves when

handling parts.

CAUTION

!

INSTALLATION

This instruction describes the installation of Part No. EHK2

accessory heaters in FFM, FMA, WAMA and WAXA fan coils.

NOTE

: Electric heaters require a minimum airflow. Minimum

airflow and motor speed selection are listed in Table 2.

Install Electric Heater Assembly
NOTE

: Ensure heater coils are not deformed or damaged during

heater installation.

1. Make sure power to unit is off.
2. Remove blower access panel of fan coil unit.
3. Remove the plate covering the opening at the back of the

top compartment.

4. Insert heater assembly into the opening, coils first. Ensure

the arrow stamped into the heater plate is orientated up to
correspond with the airflow direction. Use care not to dam-

age the coils during insertion.

5. Use the previously removed cover--plate screws to secure

the heater assembly. (See Fig. 1) Discard cover plate.

Attach Circuit Breaker Box

1. Snap the circuit breaker onto the circuit breaker bracket.
2. Install the breaker assembly using the mounting holes in the

top compartment.

3. Secure using provided screws.
4. Disconnect and discard the factory--installed high voltage

wiring harness.

5. Connect the heater assembly wiring harness to the unit--

wiring connector.

6. Use wire ties to secure wires away from sharp edges.
7. Apply the supplemental wiring diagram provided with the

heater kit over the existing wiring diagram on the fan coil.

ELECTRICAL SHOCK HAZARD

Failure to follow this warning could result in personal

injury or death.
Ensure fuse box is closed before power is turned to ON

position. There may be more than one power supply.

!

WARNING

ELECTRICAL CONNECTIONS

Refer to unit instructions for recommended wiring procedures.

Install wiring in accordance with all applicable local and national
codes. (See Table 5.) Connect heater wiring harness plug to

receptacle on fan--coil wire harness. A positive connection must be

made between plug and receptacle. Plug will interlock with
receptacle when properly seated. Harness contains both 24V

control and high--voltage wiring. Blower power is provided
through heater harness.

Power Connections

NOTE

: Heater supply circuit wire size and overcurrent protection

must comply with National Electrical Code (NEC) and UL branch
circuit requirements. (See Table 5) Wires and overcurrent
protection, integral to the heater, are not required to meet branch
circuit requirements.

Internal circuit protection of 60 amps

(maximum) is acceptable.

The 5--kW through 10--kW circuit breaker heaters can be wired for
single--supply circuit only.