1.4. Lifting
The lifting must generally be carried out with at least 4
points of support.
Also note the following requirements:
•
Safety procedures relating to lifting operations;
•
If there is damage to the packaging or equipment that
may aff ect lifting or safety in the strapping process;
•
Before hoisting, test the stability and balance of the
assembly. Avoid untwisted twisting or lifting.
To hoist/lift the units, a beam (or any similar structure)
should be used at the ends and only at the ends, as shown
in Figures 2 and 3.
The angle for the cables (or chains) should be as shown
in figure 3, the length of the cables being estimated by
this angle.
FIG. 3 - Lifting angle
• Be careful when handling, suspending and positioning
bulky equipment.
• Lift and lay the equipment carefully on the fl oor.
IMPORTANT
Before lifting the unit, check that all the panels are securely
locked. Lift and lower the unit very carefully. Shaking and
rocking the unit can damage it and aff ect its function.
The 30E units can be lifted. The coils must be protected
while the unit is being transported or handled. Use
expansion brackets or bars to distribute the hooks above
the unit. Do not rock a unit more than 15 °.
CAUTION
Never push or lift with lever any of the panels that surround
the unit. Only the frame base is designed to withstand
such pressures.
WARNING