![Carrier 16LJ-01 Installation Manual Download Page 12](http://html.mh-extra.com/html/carrier/16lj-01/16lj-01_installation-manual_2562230012.webp)
1-4. RIGGING
In case that a chiller is lifted up, check first weight of the chiller by referring its contract
specifications and then choose and use suitable lifting wires and shackles. Since 4 holes are
provided on the conners of upper tube sheet, use the holes to lift the chiller. Note that the
angle of wires shall be within 60 deg. Please refer to
Exhibit B
.
1-5. SLIDING
In case that sliding of the chiller is required, using tiltdozers (trail-builders) is recommended.
If a wire to slide the chiller is used, the wire shall be connected as shown in the figure below.
1-6. SETTING ON THE FOUNDATION
Please refer the foundation to
Exhibit C
.
Please set the Chiller on the foundation bolt position.
φ30(LJ-01)
φ40(LJ-02/03)
wire
8
Summary of Contents for 16LJ-01
Page 1: ...Absorption Chiller INSTALLATION MANUAL 16LJ 01 02 03 Original instructions ...
Page 28: ...Exhibit H LiBr solution material safty data sheet ...
Page 29: ......
Page 30: ......
Page 31: ......