2. TEST OPERATION
2-1. EXTERNAL VISUAL INSPECTION
2-1-1. External visual inspection
The Followings shall be inspected.
(1) Insulation for the Chiller shall be properly performed.
a) Pampers, service valves and sight glass shall be operable.
b) Temperature sensors and pressure gauges shall be replaceable.
c) Bar-thermometers shall be able to insert into holders provided on water headers and
solution pipes.
d) Evaporator headers shall be removable.
e) The following position shall not be insulated.
* The motor portion of the refrigerant pump
* Rupture dick
(2) No-rust shall be observed on the Chiller.
(3) No-looseness shall be observed at each flange and bolted connections.
(4) There shall be no-liquid leakage from the Chiller.
(5) No-damage shall be observed on all components of the Chiller.
(6) There shall be no-missing of all components of the Chiller.
(7) No-wire-cut shall be observed on electric wiring and piping
25
Summary of Contents for LJ
Page 1: ...Absorption Chiller INSTALLATION MANUAL LJ Model ...
Page 26: ...Fig 1 11 7 23 ...
Page 30: ... marks are the positions measured by the megger 27 ...
Page 36: ...33 ...
Page 37: ...34 ...
Page 46: ...13 Sampling of absorbent Sampling of absorbent Finished Unfinished 43 ...