5.3 System Startup
The following procedure should be followed any time the system is to be brought
online after a temporary shut down. For first-time startups or startups after any
system changes follow the procedure specified in the Initial System Startup.
5.3.1 Connect the Control Panel to the Battery Bank
Close the manual disconnect switch between the battery bank and the control
panel to bring the system online. Check that the display on the control panel
is powered up. The control panel must be powered on to continue with system
startup and commence generation.
5.3.2 Flow Water Through the System
1. Slowly open any valves downstream off the system.
2. Slowly open any valves upstream of the system, allowing water
to flow through
At this point the M300 Pico Hydro system should be fully set up and operational.
The control panel will automatically evaluate charge status and loads,
modulating generator output through opening and closing of the motorized
valve.
Summary of Contents for M300 Pico
Page 1: ...M300 Pico Hydro System Installation Operations Maintenance Version 2 0 0 1 ...
Page 2: ...Page 2 ...
Page 4: ...Page 4 ...
Page 6: ...Page 6 ...
Page 8: ...Page 8 ...
Page 16: ...Page 16 ...
Page 17: ...Page 17 4 Equipment Installation ...
Page 29: ...Page 29 5 System Operation ...
Page 36: ...Page 36 ...
Page 37: ...Page 37 6 Maintenance ...
Page 39: ...Page 39 7 Appendix ...
Page 48: ...Page 48 7 4 Equipment Drawings and Performance Curves ...