ASSEMBLY INSTRUCTIONS FOR RDC STANDARD AND EP RACKS
11.
Tie Rod Assembly:
Longer EP racks require a tie rod
assembly (see rack assembly drawings for details). The tie
rod assemblies (P/N RD02320) are to be placed as evenly
as possible among the batteries per tier (see figure 12 and
figure 13).
12. Battery Arrangement:
Install inter-cell and inter-unit
connectors and cable assemblies as determined by the
battery arrangement. Refer to Battery Installation Manual
(RS-1476) for more detail on battery connection and
initialization charge. Follow Battery Installation Manual
RS-1476 for battery installation and operation.
Tie Rod
and Cover
Serrated Nut
3/8-16 Bolt
and Lock Washer
5/16-18 Nut
and Lock Washer
Tie Rod
Bracket
Side Restraint
Rails
Tie Rod Assembly
FIGURE 12
FIGURE 11
FIGURE 13
Assembled EP2 Rack
With Corner Brackets and Front Cross Braces
Tie Rod (P/N RD02320)
Tie Rod Placement
RS02098/1011/CD
6