PTP 500 Installation Guide
phn-2508_005v000 (Mar 2013)
Page 14
4.
Preparing for installation
Safety precautions before installation
All national and local safety standards must
be followed while developing a site,
installing equipment, or performing maintenance.
Ensure that personnel are not exposed to unsafe levels of RF energy. The units
start to radiate as soon as they are powered up. Respect the safety standards
defined in the
PTP 500 and PTP 300 Series User Guide
.
Never work in front of the antenna when the ODU is powered.
Before connecting or disconnecting the drop cable from the PIDU or ODU,
always power down the PIDU.
The installation must meet the requirements in
3
Grounding and lightning protection
.
Preparing personnel
In no event shall Cambium Networks be liable for any injury to any persons or any
damage caused during the installation of the Cambium PTP 500. Ensure that only
qualified personnel undertake the installation of a PTP 500 Series link. Ensure that all
safety precautions can be observed.
Preparing inventory
Perform the following inventory checks:
•
Check that an installation report is available, based on the principles described in
the
PTP 500 and PTP 300 Series User Guide
.
•
Check that the correct components are available, as described in
1 Inventory
.
Preparing tools
Check that following specific tools are available, in addition to general tools:
•
13 mm wrench and 22 mm wrench for use with the glands.
•
RJ45 crimp tool (it must be the correct tool for the type of RJ45 being used).
•
Personal Computer (PC) with 100 BaseT Ethernet.
•
Web browser (for example Internet Explorer 7, Internet Explorer 8, Firefox 3 or
Firefox 3.5).
•
Ethernet patch cables.