Place the bypass valve in the by-pass position. Turn on the main water supply. Open a 

cold filtered water tap nearby and let run a few minutes or until the system is free from foreign 

material (usually solder) that may have resulted from the installation. Once clean, close the 

water tap.

10.

 Note this system is supplied without media installed for ease of transportation and 

simplifying site location.  Refer to the section of this manual for Media Filtration installation 

Guide/Commissioning.

11.

 Plug unit transformer into an electrical outlet. Note: All electrical connections must be 

connected according to local codes. Be certain the outlet is continually powered (unswitched/

uninterrupted).

CONTROLLER 

NOTE: The electronic control is preset at the factory so that it will begin regeneration at 

12:00 A.M. every third day. This ensures the right times for each step of the regeneration 

process. Under normal circumstances, these settings will not need to be altered and 

should not be changed.

The frequency and time of regeneration can be changed due to the following reasons:

• A need for the unit to regenerate at a different time of day (DO NOT regenerate any other 

softener/filter at the same time as the AIO, since this will interfere with the regeneration 

process).  Allow for a sufficient delay between the regeneration of equipment downstream of 

this filter for water recovery in low yielding wells.

• In conditions of high water usage and/or high levels of iron, the unit may need to regenerate 

more frequently than once every three days. The unit can be set for daily regeneration or 

to regenerate every two days.  It is not advisable in most instances to set the regeneration 

frequency for a longer period than 3 days, as the filter medium can become fouled with iron, 

rendering the unit ineffective.

  

3

Summary of Contents for PROFESSIONAL II Series

Page 1: ...OPERATIONS MANUAL RESIDENTIAL FILTRATION SYSTEMS WITH FLECK 2510 AIO CONTROL VALVE PROFESSIONAL II SERIES MODEL NO ______________________ SERIAL NO ______________________ The Blake Group B W S TM...

Page 2: ...STARTUP WATER TEST RESULTS IRON________________________PPM WATER TEST RESULTS MANGANESE_________________PPM WATER TEST RESULTS HYDROGEN SULFIDE___________PPM WATER TEST RESULTS FEEDWATER pH__________...

Page 3: ...design Do not use where water is microbiologically unsafe Installation Requirements WATER PRESSURE A minimum of 30 psi of water pressure 2 7bar is required for regeneration valve to operate effectivel...

Page 4: ...er tank from venting backwards up the feed water plumbing 5 If not factory installed assemble the deflector to the distributor tube Deflector Installation Put a thin layer of silicone lube around insi...

Page 5: ...A M every third day This ensures the right times for each step of the regeneration process Under normal circumstances these settings will not need to be altered and should not be changed The frequenc...

Page 6: ...e this occurs a regeneration cycle will be initiated at the Set Regeneration Time Water flow through the valve is indicated by the Flow Indicator that will flash in direct relationship to flow rate Ti...

Page 7: ...event of power failure the control shifts into a power saving mode The control stops monitoring water usage and the display and motor shut down but it continues to keep track of the time and day for a...

Page 8: ...le button again The service icon will stop flashing Regenerating Immediately Press and hold the Extra Cycle button for five seconds 1 The timer advances to Regeneration Cycle Step 1 backwash and begin...

Page 9: ...eration time may be changed to accommodate households with varying schedules however once set to meet water quality requirements the cycle duration times should not be changed 1 Backwash 14 minutes Du...

Page 10: ...gle Tank DO Day Override 3 Days between Regenerations RT Regeneration Time 12 00 AM Regeneration Time BW Backwash 14 Minutes for Backwash Cycle BD Air Draw 40 Minutes for Air Draw Cycle RR Rapid Rinse...

Page 11: ...iser tube to ensure that no filtration media or gravel falls down into the riser tube The riser tube should be firmly seated and centered in the tank and should be flush with the top of the tank openi...

Page 12: ...backwash The backwash cycle should continue unit the water runs clear The valve can ow be cycled to service and the bypass valve opened allowing treated water to enter the household piping Caution mos...

Page 13: ...the unit and contact technical support 2 Regen Failure The system has not re generated for more than 99 days or 7 days if the control type has been set to Day of Week Perform a Manual Regeneration to...

Page 14: ...2 8 216 259 2 324 432 Media Wgt cf Service Rate GPM perSq Ft Backwash Rate GPM per Sq Ft Bed Depth Inches Percent Bed Expansion 50lbs 5 12 to 18 24 to 36 20 to 40 35 to 40LBS 3 5 to 5 10 to 12 30 to 3...

Page 15: ...NOTES...

Page 16: ...DISTRIBUTED BY AIO MANUAL Rev APR 2018 Blake Water Solutions 4 New Park Road East Windsor CT 06088 Tel 860 243 1491 The Blake Group B W S TM P N XO2510AIO...

Reviews: