4.4.2 Connecting the Gas Line

Please note the following items when connecting the sample
gas line (NPT 1/4") on heated probes to prevent thermal
bridges:

• Choose the shortest possible screw connection.
• Shorten the connection pipe for the sample gas line as

much as possible. To do so, remove the insulation around
the sample gas line. This is done by loosening the fixing
bolts.

CAUTION

Fragile

The insulation is fragile. Handle with care, do not drop.

After connecting the sample gas line it must be braced and se-
cured with the clamp.

Long sample gas lines may require additional support clamps
along the way to the analysis system! Once all lines have been
connected and checked for leaks, carefully reinstall and secure
the insulation.

WARNING

Gas emanation

Sample gas can be harmful to the health!

Check the lines for leaks.

4.4.3 Connecting the calibrating gas line (optional)

Connecting the calibrating gas line requires a Ø6 mm or Ø1/4”
pipe fitting.

If the calibrating gas connection was ordered with check
valve, a Ø6 mm or Ø1/4” pipe can be connected directly to the
check valve.

4.5 Connecting the Blowback and Pressure Vessel
(Optional)

The air lines must be connected carefully and properly, using
suitable fittings.

If the probe is equipped with pressure vessel for efficient
blowback (optional), a manual shut-off valve (ball valve) must
be installed in the air supply, immediately upstream from the
pressure vessel.

NOTICE

The operating pressure of the compressed air (inert gas) re-
quired for blowback must always be higher than the process
pressure.

Required pressure differential min. 3 bar (44 psi).

DANGER

Broken pressure vessel

Gas leak, danger due to flying parts.

Maximum operating pressure of the pressure vessel 10 bar
(145 psi)!

The operating pressure reduces based on the operating
voltage (see solenoid valve type plate).

4.6 Electrical connections

WARNING

Hazardous electrical voltage

The device must be installed by trained staff only.

CAUTION

Wrong mains voltage

Wrong mains voltage may damage the device.

Regard the correct mains voltage as given on the type plate.

Electric strength test

The necessary tests of all assemblies required to be tested
were carried out at the factory (test voltage 1 kV or 1.5 kV de-
pending on component).

To check the electric strength again yourself, only do so on the
respective individual components.

• Now perform the electric strength test against earth.

4.6.1 Connection via Terminal Strip

The probe has regulated, adjustable heating. The supply
voltage is 115 V AC, 50/60Hz or 230 V AC, 50/60 Hz (see type
plate).

The device is already wired to the controller.

Inside the controller housing is a terminal block for connect-
ing the mains supply and the alarm output. The connection to
the included terminal blocks is shown in the attached connec-
tion diagram. For this purpose the plugs can be removed from
their sockets and reinserted once wired. The pin assignment is
also printed onto the board.

If the heat dissipation is very high near the probe due to the
application, the customer must install a shield to protect the
probe and regulator.

4.6.2 Heated Pressure Vessel (Optional)

A heated compressed air tank can optionally be used for blow-
back. Heated via self-regulating PTC heating cartridge to pro-
tect against frost.

If the heater was ordered with the probe, it is pre-wired.

When retrofitting with a heater, it can be powered by the
probe control unit.

Connect the connecting cable for the heater (mains connec-
tion 115/230 V AC) per the enclosed wiring diagram.

4.6.3 Heated Extension (Optional)

The unit can optionally be ordered with heated extension.
Heated via regulated heating tape with Pt100, preventing fall-
ing below the sample gas dew point at the sample point. The
unit cannot be retrofit with a heated extension.

The connection cable for the heated extension (mains connec-
tion 115 or 230 V AC) must be connected per the enclosed con-
nection diagram.

10

Bühler Technologies GmbH

BX460061 ◦ 09/2021

Summary of Contents for GAS 222.31

Page 1: ...061 Version 09 2021 Ref 998BX460061 Analysentechnik Kurzanleitung Sonden deutsch 2 Brief Instructions Probes english 8 Notice de montage Sondes fran ais 14 Gu a r pida Sondas espa ol 20 chinese simpli...

Page 2: ...tikel Nr Werkstoff Elektrische Versorgung 1 3 Lieferumfang 1 x Gasentnahmesonde 1 x Flanschdichtung und Schrauben Produktdokumentation Anschluss und Anbauzubeh r nur optional 2 Sicherheitshinweise Das...

Page 3: ...Danach wird die Sonde unter Verwendung der beigef gten Dichtungen und Schrau ben am Gegenflansch befestigt 4 3 Isolierung Bei beheizten Sonden sind die blank liegenden Flanschteile und ggf der Einbaus...

Page 4: ...R Bruch des Druckluftbeh lters Gasaustritt Gefahr durch umherfliegende Teile Maximaler Betriebsdruck f r den Druckluftbeh lter 10 bar 145 psi Der Betriebsdruck reduziert sich je nach Betriebsspannung...

Page 5: ...C Solltemperatur 180 C Arbeitsbereich 10 C 5 1 2 Erweiterte Funktionen bei integriertem Regler f r beheizte Verl ngerung optional Im Display wird abwechselnd Prob Temperatur Adapter AdOn Temperatur V...

Page 6: ...ahlweise Celsius oder Fahrenheit Anzeige Temperatur Wahlmen Wahlmen Exit Wahlmen Exit Anzeige Top Settings R cksp lintervall Alarm Wahlmen Sondentemperatur R cksp lzeit ____ Einstellbereich Setzen der...

Page 7: ...der Ori ginalbetriebsanleitung auf der beigef gten CD oder im Inter net unter www buehler technologies com 7 Service und Reparatur Eine ausf hrliche Beschreibung des Ger tes mit Hinweisen zur Fehlers...

Page 8: ...1 x Sample gas probe 1 x Flange gasket and screws Product documentation Connection and mounting accessories only optional 2 Safety instructions The equipment must be installed by a professional famil...

Page 9: ...es completely insulate any exposed flange areas and if applicable the connection piece to absolutely prevent thermal bridges The insulating material must meet the application requirements and be weath...

Page 10: ...electrical voltage The device must be installed by trained staff only CAUTION Wrong mains voltage Wrong mains voltage may damage the device Regard the correct mains voltage as given on the type plate...

Page 11: ...ilt in blowback control optional After switching on the probe blowback will always first be ini tiated Blowback is always indicated by the display alternating between the temperature and bbon blow bac...

Page 12: ...rature Selection menu Selection menu Exit Selection menu Exit Display Top Settings Blowback interval Alarm Selection menu Probe temperature Blowback time ____ Setting range Setting the alarm hysteresi...

Page 13: ...r s manual on the included CD or online at www buehler technologies com for maintenance informa tion 7 Service and Repair Please refer to the original operator s manual on the included CD or online at...

Page 14: ...213 001 230V 50 60Hz 440W material 1 4571 1 4408 PTFE Read manual 1 3 Contenu de la livraison 1 sonde de pr l vement de gaz 1 x Joint de bride et vis Documentation de produit Accessoires de raccordeme...

Page 15: ...e des joints et vis joints 4 3 Isolation Pour les sondes chauff es les parties de la bride nu et le cas ch ant les supports de montage doivent tre enti rement isol s apr s le montage la formation de p...

Page 16: ...ar 44 psi DANGER Rupture du r servoir de gaz comprim Sortie de gaz danger de composants projet s La pression de fonctionnement maximale pour le r servoir de gaz comprim est de 10 bar 145 psi La pressi...

Page 17: ...il 10 C 5 1 2 Fonctions tendues avec r gulateur int gr pour rallonge chauff e en option L cran indique en alternance Prob Adaptateur de temp rature AdOn Rallonge de temp rature 5 1 3 Fonctions tendues...

Page 18: ...Temp rature Menu de s lection Menu de s lection Exit Menu de s lection Exit Affichage Top Settings Intervalle de r trolavage Alarme Menu de s lection Temp rature de sonde Dur e de r trolavage ____ Pla...

Page 19: ...ns le mode d emploi original pr sent sur le CD fourni ou sur Internet en allant sur www buehler technolo gies com 7 Service et r paration Vous trouverez une description d taill e de l appareil ainsi q...

Page 20: ...408 PTFE Read manual 1 3 Volumen de suministro 1 x sonda de muestreo 1 x junta de brida y tornillos Documentaci n del producto Accesorios de conexi n y de ampliaci n solo opcional 2 Avisos de segurida...

Page 21: ...islamiento Con las sondas calentadas tras el montaje deben aislarse completamente las partes vac as de las bridas y en caso dado tambi n los cuellos de conexi n de esta forma es posible evi tar los pu...

Page 22: ...cesaria m n 3 bar 44 psi PELIGRO Rotura del recipiente de aire a presi n Salida de gas riesgo de proyecci n de piezas Presi n de funcionamiento m xima para el recipiente de ai re comprimido de 10 bar...

Page 23: ...cap tulo Uso y funcionamiento Los ajustes perdeterminados son Unidad C Temperatura de ajuste 180 C Rango de trabajo 10 C 5 1 2 M s funciones del regulador integrado para la prolongaci n con calentami...

Page 24: ...ra Men de selecci n Men de selecci n Salir Men de selecci n Salir del submen Pantalla Top settings Intervalo de retrolavado Alarma Men de selecci n Temperatura de sondas Tiempo de retrolavado ____ Opc...

Page 25: ...se pueden encontrar en el CD que se incluye y en Internet www buehler technologies com 7 Servicio y reparaci n Para obtener una descripci n m s detallada del dispositivo y recomendaciones recomendaci...

Page 26: ...n Deutschland 49 0 2102 4989 0 49 0 21 02 49 89 20 1 1 ID 1 2 GAS 222 31 100107323 462231009902000112213 001 230V 50 60Hz 440W material 1 4571 1 4408 PTFE Read manual 1 3 1 x 2 a b c d a b c 3 20 C 50...

Page 27: ...2 NPT 1 4 G1 2 NPT 1 4 G1 8 G1 4 NPT 1 4 1 1 2 GAS 222 xx ANSI GAS 222 xx AMEX 4 4 1 G3 8 4 4 2 NPT 1 4 4 4 3 6 mm 1 4 6mm 1 4 4 5 3 bar 44 psi 10 bar 145 psi 4 6 1 kV 1 5 kV 4 6 1 115 V AC 50 60Hz 23...

Page 28: ...GAS 222 31 4 6 3 Pt100 115 230 V AC 5 5 1 5 1 1 C F C 180 C 10 C 5 1 2 Prob AdOn 5 1 3 bbon 5 1 4 SV SSR RSS 5 2 3 28 B hler Technologies GmbH BX460061 09 2021...

Page 29: ...ALAr E ___ C F C 5s 50 C 200 C 122 F 392 F ____ 5 C 30 C 50 C 200 C 122 F 392 F 5 C 30 C 5s 99s Blow back controller AdOn bbc tEMP ALAr E E ____ ___ __ __ __ 0 5 min 99h59min 5 59 s ctrl tInt t_bb 29...

Page 30: ...GAS 222 31 6 CD www buehler technologies com 7 CD www buehler technologies com 30 B hler Technologies GmbH BX460061 09 2021...

Page 31: ...H Harkortstra e 29 40880 Ratingen Deutschland 49 0 21 02 49 89 0 49 0 21 02 49 89 20 1 1 o 1 2 GAS 222 31 100107323 462231009902000112213 001 230V 50 60Hz 440W material 1 4571 1 4408 PTFE Read manual...

Page 32: ...C 50 C 4 F 122 F 4 4 1 4 2 4 3 4 4 GAS 222 PAV01 3 2 1 DN65 PN6 DN3 150 2 G3 4 NPT 1 4 G3 8 1 6 1 4 2 NPT 1 4 G1 2 NPT 1 4 G1 8 G1 4 NPT 1 4 1 1 2 GAS 222 xx ANSI GAS 222 xx AMEX 32 B hler Technologie...

Page 33: ...GAS 222 31 4 4 1 G3 8 4 4 2 NPT 1 4 4 4 3 6 1 4 6 1 4 4 5 3 44 psi 10 145 psi 4 6 1 1 5 4 6 1 115 AC 50 60 230 AC 50 60 33 B hler Technologies GmbH BX460061 09 2021...

Page 34: ...GAS 222 31 4 6 2 115 230 AC 4 6 3 Pt100 115 230 AC 5 5 1 5 1 1 C F C 180 C 10 C 5 1 2 Prob AdOn 5 1 3 bbon blow back on 5 1 4 SV SSR RSS 5 2 3 34 B hler Technologies GmbH BX460061 09 2021...

Page 35: ...F 392 F Exit Exit Top Settings ____ 5 C 30 C 50 C 200 C 122 F 392 F 5 C 30 C 5 99 Add on Blow back controller AdOn bbc tEMP ALAr Exit E Exit E ____ ___ __ __ __ 0 5 99 59 5 59 ctrl tInt t_bb Control m...

Page 36: ...GAS 222 31 6 www buehler technologies com 7 www buehler technologies com 36 B hler Technologies GmbH BX460061 09 2021...

Page 37: ...GAS 222 31 1 Connection diagram heated pressure vessel Heater Operating voltage 115 230 V AC 200 W 37 B hler Technologies GmbH BX460061 09 2021...

Page 38: ...ed extension Pt100 heated extension Pt100 probe Power supply extension heated extension Power supply extension Blowback status Blowback solenoid valve Status Automatic Manual Sample gas solenoid valve...

Reviews: