4 ADJUSTING THE CONSTRUCTION
› Check the top side of the construction with a laser or a level.
› If necessary, adjust the construction
› Move the vertical poles upward untill the top side of the contruction is completely level.
› If necessary use some provisional filling.
4.a LEVELNESS
› Check the perpendicularity trough the following dimension. (L1 ± 2mm !)
› Also check the diagonals of the top side.
› If necessary, the pole supports allow a small adjustment..
L1
L1
L2
L2
4.b PERPENDICULARITY
L3
L3
Pole Support
Floorplate 20x20
Groundanchor
Sideview
Topview
› Once everyting has been adjusted, tighten all the bolts.
› Remove the provisional filling
(L1 ± 1/8” !)