1.1.3
Turning ON the Power After Installation
Before Turning ON the Power
After completing the machine installation, check the following points before
turning on the power.
Make sure that all bolts are tightened securely.
Make sure that all connectors are connected properly.
Make sure that all hoses and air pipes are connected properly.
If the machine is equipped with any optional external equipment (Chip
Conveyor, Pallet tool etc), make sure that the electrical cable and
hydraulic/pneumatic pipes are connected correctly.
Check the input voltage and the R/S/T (L1/L2/L3) phases of input power.
After turning the Machine Power On.
Remove any clamps that could not be removed with the power off immediately
after turning power on.
To run in the new spindle, follow the thorough warm up procedure given in the
Operating Manual.