STEP 1 

-

 

DETERMINE THE FENCE LINE, POSTHOLE DEPTH AND CENTRES

We recommend you plan your fence set out/post 

position on a piece of paper to save unnecessary 

digging.

Accurately determine the boundary line to where 
the fence will be installed, (in some cases a 

surveyor may be required) mark this with a string 

line as per the diagram below.

Determine your posthole centres using the table 

below as a guide and mark out your posthole 

positions on the ground with line marking paint.

NOTE-

Postholes can be dug by hand or with a mechanical auger. Use the footing depth table on page 5 to 

determine your posthole depth and diameter.

Recommended footing depths listed here are for wind regions A & B plus terrain categories 2.0, 2.5 & 

3. If you are building your fence in a cyclonic wind area, on top of a hill, adjacent to an escarpment, on 

a ridge or in terrain category 1, you will need engineering advice beyond the scope of this publication.

Position the 

boundary line half 

the depth of the post

Summary of Contents for SLEEKWALL SOLID

Page 1: ...SLEEKWALL SOLID A STEP BY STEP GUIDE TO INSTALLING YOUR FENCE INSTALL GUIDE...

Page 2: ...DTHIS TOOLS LIST It is recommended that the reader pays particular attention to those items identified as IMPORTANT in this manual to ensure satisfactory long term performance IMPORTANT the table in S...

Page 3: ...items are not included but one type of post and cap are required for installation 145 x 16 x 1780mm TGV PALING 30 x 30 PALING CHANNEL CHANNEL COVER CLIP CHANNEL ENDS CAPS LEFT RIGHT TEK SCREWS 65 x 6...

Page 4: ...r posthole centres using the table below as a guide and mark out your posthole positions on the ground with line marking paint NOTE Postholes can be dug by hand or with a mechanical auger Use the foot...

Page 5: ...imber posts ot concrete blocks etc TGV Paling Length 65 x 65 Post Hole Centres In between Post Measurements 1780mm Paling 1865mm 1800mm Wall Height Hole Depth into Firm Earth or Clay 900mm 450mm 1200m...

Page 6: ...e concrete is being poured Avoid using quick setting concrete as it can be corrosive to aluminium posts IMPORTANT Allow 75mm min from edge of post to edge of ground Slop top of concrete away from post...

Page 7: ...same principal of the gap between a string line and the posts works for both in ground and flanged posts this will ensure a straight line of posts Refer to page 6 for a diagram of this Refer to the ta...

Page 8: ...round it may be required that you step your fence from bay to bay Once a height has been established for all your channels with the tek screws supplied screw your channel directly to your post whilst...

Page 9: ...hey are all stacked Then place the tongue cover over the last paling and screw into place If you are doing a lower height than 1800mm you will need to divide the height of your wall into the number of...

Page 10: ...is to use either a rubber mallet or the rubber handle of your hammer Insert one edge of the cover clip into the channel then with the rubber mallet hammer handle from either the top or bottom Tap the...

Page 11: ...DE CAPPING INSTALLATION STEP 6 FITTING CHANNEL CAPS Once all the palings have been installed we have an optional cap to cover the profile of the slat channel system These consist of a left and right h...

Page 12: ...S Yes we have a 10 year warranty on our products If you are in a coastal zone then an increase of cleaning and maintenance will be required We do not recommend the product to be in direct contact with...