'Where the terminal is within 1m of any plastic material, such material should be shielded from the effects of
the combustion products of the flues
NOTE:- Whilst the dimensions in BS 5410 are shown in the table, it is stressed that possible variances
in local site conditions may not always be obvious and that if in any doubt the dimensions in brackets
should be observed.
Page 27
5.2 TERMINAL GUARD
The guard supplied should be fitted to the boiler casing as
shown in fig 5.2
Fig 5.2
Section 6 - Balanced Flues
NOT APPLICABLE
Section 7 - Commissioning
7:1 COMMISSIONING BOILER
It is essential in the interest of boiler efficiency and reliable performance that once the Boiler has been
installed it is first commissioned by a qualified engineer.
If an engineer is not known Boulter Buderus will be please to provide details of a commissioning and servicing
engineer from their register.
7:2 RESPONSIBILITY
It is the responsibility of the installer to ensure that the boiler is properly commissioned. It is essential that the
commissioning procedures detailed in this manual are carried out preferably by a qualified OFTEC engineer
using recognised test equipment.
K
Horizontally from any Opening, Air Brick, Window or Door
600
Page 38 of 57
Installation & maintenance manual for Camray 5 Combi External Boilers
14/04/2005
file://D:\PL61500\PL61500.htm