48/64 Commissioning
Bosch Rexroth AG
, Accumulator shut-off block type ABZSS, 0532VAW, RE 50129-B/02.19
8.1.2 Commissioning process
For commissioning, the following work steps have to be performed:
▶
Compare the pressure adjustment of the type-examination tested pressure
relief valve with the maximum admissible operating pressure of the hydraulic
accumulator. The pressure adjustment of the type-examination tested pressure
relief valve must not exceed the admissible operating pressure of the hydraulic
accumulator.
▶
Close the manual relief.
▶
Open the system shut-off cock.
▶
Bleed all channels on the actuator side. Observe the specifications of the
machine/system manufacturer.
▶
Check the electrical signals (optional).
Commissioning of the accumulator shut-off block is completed.
The adjustment of sealed pressure relief valve must not be changed!
8.2 Re-commissioning after standstill
Contact Bosch Rexroth for re-commissioning after a standstill of more than
3 months.
For re-commissioning of the accumulator shut-off block, proceed as described in
chapter 8.1 "First commissioning".
Bleeding
2-way cartridge valve
check
Standstill for more than 3
months
Re-commissioning