Bosch Solar Module c-Si M 60 EU I Bosch Solar Module c-Si M 60 S EU I Bosch Solar Module c-Si P 60 EU I Bosch Solar Module c-Si M 48 EU I Bosch Solar Module c-Si M 48 S EU 
Module manufacturer code 14, 17, 23

  

      

Bosch Solar Energy AG

10 | Electrical connection | Grounding | Mainenance and care 

Important note! 
Never remove or insert plug-in contacts 
when the system is under load! 

  The connection cables should be installed in such a 

way that the minimum bend radius of 60 mm is com-
plied with. 

  The connection cables are equipped with a high-qual-

ity plug system (original MC4) for photovoltaics 
which latch on if correctly connected. The plugs are 
marked with their respective polarity symbols (see 
datasheet).

 

Ensure the polarity symbols are in the right position 
when connecting plug connectors and modules and 
when connecting solar modules to the inverter. Incor-
rect polarity can permanently damage all technologi-
cal components in the system. 

  All solar module frames and the support structure 

must feature highly conductive connections to a 
protective grounding system to eliminate the risk of 
electric shocks. We recommend installing the ground-
ing system outside the building. Observe local statu-
tory regulations and recommendations given by the 
inverter manufacturer and your insurance company.  

Particularly in exposed locations, sufficient lightning 
protection is recommended. Integration into existing 
lightning-protection systems must occur in observance 
of current country-specific norms and regulations. The 
respective drill holes for grounding are marked on the 
reverse side of the module frame.
Please perform the following grounding measures:

7 Grounding

Important notice!

Earthing / Grounding Requirements
In accordance with AS/NZS 5033 clause 4.4.2.2 PV mo- 
dules and mounting frame earth connections are to be a 
purpose-made fitting providing earthing or bonding 
connections or purpose-made penetrating washers or 
equivalent between the PV modules and mounting frame 
for the connection of dissimilar metals purpose-made 
fittings are installed to manufacturer’s instructions.

  Cable lugs, earthing termination and bonding cables   

     are to be fixed by stainless steel bolts, washers and
     penetrating washers to aluminium frames.

  Earthing or bonding connections MUST BE arranged 

so that the removal of a single module earth connec-
tion will not affect the continuity of the earthing or 
bonding connections to any other module.

Little maintenance and care is required to deliver opti-
mum solar module performance. We recommend the 
following items are checked or the following action 
taken on a half-yearly basis to ensure optimum system 
performance:

 

If modules are heavily soiled or dirty in places, from 
bird droppings, for instance, it is recommended to 
clean module glass surfaces with a soft brush and 
lime-free water at module temperature.  Do not use 
aggressive cleaning agents, acids or alkaline solu-
tions.

  Under no circumstances should there be increased 

pressure during cleaning e.g. by pressing a brush so 
strongly during cleaning, that this can lead to damage 
to the antireflective coating of the glass for example.   
In the case of intensive soiling, repeated cleaning or 
soaking is recommended. 

  Any finger prints on the anti-reflection solar glass can 

be removed with a microfiber cloth and distilled 
water or isopropanol. 

  Check electrical and mechanical connections to 

ensure they are clean, tightly fastened and intact. Any 
anomalies must be remedied immediately.

8 Maintenance and care

Summary of Contents for c-Si M 60 S EU

Page 1: ... I Bosch Solar Module c Si M60 S I Bosch Solar Module c Si P60 Robert Bosch GmbH Australia Operating instructions for products with module manufacturer code 14 17 23 Issue 08 2013 Installation and Operation Guide Crystalline Solar Modules Bosch Solar Module c Si M 60 EU ...

Page 2: ...l warranty and guarantee claims towards us shall lapse We reserve the right to update the information in this guide without prior notice The installation setup and commissioning of solar mod ules requires a high level of expertise and experience and therefore must be performed solely by specialists e g a specialist electrician who can verify the successful com pletion of suitable training 1 Introd...

Page 3: ...er than 120V Even when the light intensity is low one must reckon with the full atrest voltage of the modules that is to Important notice say in the course of setup one must always exercise the greatest caution with regard to electrical faults e g short circuits The separation of conductors which carry direct cur rent can lead to light arcs Therefore prior to perform ing any work on the solar syst...

Page 4: ...cleaning the angle of inclination must amount to at least 10 For optimized selfcleaning a 15 minimum angle of inclination is recommended Always ensure that the reverse side of the module is well ventilated Attention Due to heat accumulation under the modules there is an increased fire hazard associated with rooftop installations which do not meet the aforementioned requirements You should mount th...

Page 5: ...rrosion between the solar module and substructure is prevented when different materials are used Fasten the solar modules in such a way that they are able to withstand all anticipated loads and any impacts caused by weather conditions Use only corrosion resistant screws to install modules Ensure the support structure does not allow rainwater or condensation water to reach the cable screw con necti...

Page 6: ...r Energy AG 6 Installation guidelines pressure load rating 2400 Pa pressure load rating 5400 Pa without central support with central support screw fasten ing to assem bly holes fastener clamp system on long sides fastener clamp system on short sides slide in or lay in system slide in or lay in system table 2 vertical fastening area 500 500 360 440 360 440 400 200 400 300 300 central support clamp ...

Page 7: ...olar Energy AG Installation guidelines 7 table 3 horizontal fastening area central support clamp section junction box pressure load rating 2400 Pa pressure load rating 5400 Pa without central support with central support screw fasten ing to assem bly holes fastener clamp system on long sides fastener clamp system on short sides slide in or lay in system slide in or lay in system 500 500 300 300 40...

Page 8: ...3mm and have a surface area of at least 2mm width When fastening modules in the area of the module or drainage corners the following should be observed If corner clamps are used a minimum cover area of 28mm of the clamp must be ensured length of the assembly clamp The assembly clamp must overlie by min 8mm and max 12mm on the frame depth of assembly clamp figure 2 reverse side c Si M 60 and M 60 S...

Page 9: ...uali fied specialists In the process they must comply with the relevant industrial standards and regulations for PV systems such as the German Association for Electrical Electronic Information Technologies regulations DIN standards German Association of Energy and Water Industries guidelines the network operator s technical connection conditions and employers liability insurance associations accid...

Page 10: ...ures 7 Grounding Important notice Earthing Grounding Requirements In accordance with AS NZS 5033 clause 4 4 2 2 PV mo dules and mounting frame earth connections are to be a purpose made fitting providing earthing or bonding connections or purpose made penetrating washers or equivalent between the PV modules and mounting frame for the connection of dissimilar metals purpose made fittings are instal...

Page 11: ...rd of organic material e g dry grass hay combustion in the vicinity of the system Avoid bending during transport or when unpacking Do not drop the modules Do not place any objects on the modules Do not handle the modules using sharp objects In the course of storage and transport it must be ensured that each solar module is sufficiently rein forced The stacking of packaging units can cause damage t...

Page 12: ...de Bosch Solar Energy AG Robert Bosch Straße 1 99310 Arnstadt Germany Tel 49 0 3628 66 44 0 Fax 49 0 3628 66 44 1133 www bosch solarenergy com ...

Reviews: