To replace the Cassette in the water valve: 

1.

 

Turn pump off 

2.

 

Loosen the bolt on band clamp and remove the band clamp and clear lid. 

3.

 

Remove the turbine and old cassette by sliding them off of the center shaft. 

4.

 

Install the new cassette by sliding it onto the center shaft.  Spin the gears and make 
sure the cassette drops all the way down and the lower gears engage with the gear 
train on the housing perimeter.   

5.

 

Place the turbine on the center shaft gear side down.  Make sure the gear on the 
turbine engages the upper gear on the cassette.  Spin the turbine several times and 
observe the white bottom plate is slowly turning.  If it does not the cassette is not in 
the full “down” position and the lower gear is above the gear train on the housing 
perimeter. 

6.

 

Check positioning of large 0-ring on the clear lid. 

7.

 

Align the center shaft on the guide pin hole in the center of the clear lid and gently 
push the lid down.  The lid should seat firmly seat on the top of the valve housing with 
no wobble.  

8.

 

Replace the band clamp and tighten the bolt firmly.  Do not over tighten. 

 
 
Thank you for purchasing a Blue Square Q360 In-Floor Cleaning System!  With over 20 
years of pool building and in-floor knowledge, this system was designed with you and the 
homeowner in mind.  This cost effective and efficient system is truly innovative with a very 
simple approach to installation and repair; making it easy for the homeowner to keep 
their pool clean and, should there be a problem to arise, easy to fix.  We are here to 
answer questions, resolve issues and provide exceptional customer service.    
 
 

Blue Square Manufacturing, LLC

 

525 East Baseline Road 

Suite 107 

Gilbert, AZ  85233 

Office 480.612.6880  Toll Free 800.277.4150 

[email protected] 

 

Summary of Contents for Q360

Page 1: ...Page 1 V14612INSLM V Va al lv ve e I In ns st ta al ll la at ti io on n a an nd d M Ma ai in nt te en na an nc ce e G Gu ui id de e ...

Page 2: ...arranty fax or email a System Design Form provided by Blue Square along with a scaled pool plan for a FREE certified In Floor Design New pool construction only Email plans bluesquaremfg com Fax 888 282 6955 If the pool plan design or dimensions change during excavation a revised plan must be submitted to Blue Square in order to maintain warranties Install the valve above ground at finished pool wa...

Page 3: ...en gear design allows for effective pass through of debris greatly minimizing annoying cleaning system disruptions and lowering maintenance costs even further over other in floor systems The Innovative pressure safe valve design protects your system by ensuring that one port is always open Large 2 inlet and 6 2 ports maximize flow rate Reinforced space age molded construction weathers the elements...

Page 4: ...sts position the valve as close as possible to the swimming pool or water feature The valve should be at least five feet away from the water s edge Check the bonding codes in your area The low profile design the quiet and smooth operation of the Q360 Water Valve allows for the valve to be inconspicuously hidden by an irrigation box or landscaping Although servicing the valve is very rare the valve...

Page 5: ... or a different elevation body of water to prevent drain back or equalization See Fig A 1 3 Fig A 1 3 Follow the design plan to position and stake the cleaning head locations Each head has a designated nozzle that has a precise cleaning radius Perimeter heads have a one foot overlap Mark the cleaning radius around each stake ...

Page 6: ...riser with no reaming required These stub ups should be perpendicular to the slope of the pool floor Plumbing the Valve see Plumbing the System Diagram Remove the Cassette Gears during pressure testing to allow for equal distribution of pressure down all 6 ports or zones Store the Cassette with the jets for reinstallation at start up Position the O ring on the valve housing in the O ring groove Al...

Page 7: ...ll outlet ports on the valve are not needed use the Y Pipe as noted in the plan to aid in efficiency and reduce plumbing costs Note Surface returns can be applied to the unused port Never tie a raised spa bank with any plumbing from a lower body of water and drain down Consult the design plan for proper connections Auxiliary Equipment Heaters To compensate for heater system pressure drops plumb he...

Page 8: ... stub up ensuring collars sit at a height to accommodate approximately of final finish material Clean off all burs and debris 3 Insert test plug in each stub up 4 Attach a blower assembly unit blower check valve air water supply and connectors call Blue Square for assembly instructions to the blower plate or directly to the valve 5 Turn on blower and water supply to fill the lines 6 Starting at th...

Page 9: ...the top of the valve housing with no wobble If it does not sit firmly remove the turbine and press the cassette down into the gear train 8 Replace the band clamp and tighten the bolt firmly Do not over tighten 9 Turn on the system and allow it to cycle until all of the protective caps are blown free from the collar and to allow any additional construction debris to be blown out of the pipes 10 Aft...

Page 10: ...the water flows from the jet nozzle on each side of dirty spot are not apposing one another To change the cleaning jet flow direction press the jet down 5 6 times while it is in the up position and the water is flowing out of the nozzle Actions Cleaning jet advances but is not cleaning dirt remains near the jet Solution Remove the cleaning jet with the jet removal tool Check for debris lodged in t...

Page 11: ...meter 6 Check positioning of large 0 ring on the clear lid 7 Align the center shaft on the guide pin hole in the center of the clear lid and gently push the lid down The lid should seat firmly seat on the top of the valve housing with no wobble 8 Replace the band clamp and tighten the bolt firmly Do not over tighten Thank you for purchasing a Blue Square Q360 In Floor Cleaning System With over 20 ...

Reviews: