3  INSTALLATION 

 

The boiler must be installed by a qualified person. The size and features of the room must comply with 
the relevant safety standards. All regulations involving the safety of technical installation must be 

complied with. 
Before connecting the heating system advise to carried out a tubes washing to prevent that impurity 
put in jeopardy the boiler corrected functioning. 

 

Flue gas be discharged through pipes with a diameter no less than that of the hood and connected to 
a stack of suitable capacity. The stack must be of a suitable size and height to ensure minimum draft 

as per specification and thermally insulated as prescribed. 
The connection of the burner to the fuel piping must be carried out by qualified personnel following the 

instructions with the burner 
The electric connecting must carried out stable and safe. It’s more important to carry out the electric 
connecting to the feeding line under the laws in force. 

Before electric connecting it must be checked an efficient earthing wiring because this is a basic safety 
requirement. 
Not use the water-pipes and the gas-pipes for earthing. 

Besides verify the wiring suitable for the equipment and burner maximum power adsorption. 

 

3.1  BURNER MATCHING 

 

For installation of the burner, the electrical connections and the 

necessary settings, consult the burner instruction manual. 
Ascertain that the correct type of burner has been  
chosen for the boiler, checking the technical specifications of both. 

The burner  blast  tube must be sized as shown  in the picture here 
beside. 

Model 

Cement Hole 

on door 

Ø (mm) 

Door 

Thickness 

S (mm) 

Blast tube burner 

length min-max 

L (mm) 

Internal Furnace 

Diameter 

(mm) 

Internal Furnace 

Length 

(mm) 

SIMPLEX 35 

110 

135 

150/180 

296 

400 

SIMPLEX 50 

110 

135 

150/190 

296 

490 

SIMPLEX 80 

110 

150 

165/205 

345 

555 

 

 

3.2  OPERATING 

 

Starting up the boiler 

Before starting up the boiler, check that: 

  the system is full of water and that the pressure on the gauge does not exceed the rated value of 

1,5

÷

2 bar 

  the stack was built in compliance with the current regulations, perfectly free and there is not air 

infiltration 

  the connection between boiler and stack is perfectly tight-proof 

  the flanges or fittings are  perfectly sealed and the power supply voltage corresponds to that 

required for the boiler 

  the burner rated values (power  supply and nozzle flow) are compatible with the boiler and that 

there is no air infiltration in the fuel oil pipes 

  all air has been relieved from the system 

  pump delivery and lift suitable for heating system delivery 

 

Summary of Contents for SIMPLEX 35

Page 1: ...INSTRUCTIONS MANUAL FOR BOILERS MODELS SIMPLEX 35 SIMPLEX 50 SIMPLEX 80 n 1460080 EN Upd 01 07 09...

Page 2: ...FLOOR STANDING WATER BOILERS MOD SIMPLEX n 1460080EN 07 2009 2...

Page 3: ...INDEX 1 IMPORTANT 3 2 BUILDING CHARACTERISTICS 4 2 1 TECHNICAL DATA 5 2 2 CONTROL PANEL 6 3 INSTALLATION 7 3 1 BURNERMATCHING 7 3 2 OPERATING 7 4 MAINTENANCE 8 5 WIRING DIAGRAM 9...

Page 4: ...ate a hazard The Manufacturer cannot be held liable for damage caused by improper or unreasonable use q Before cleaning or servicing the boiler disconnect from the power mains by operating the switch...

Page 5: ...n the smoke side are so limited as the allow a wide range of choice for operation with gas oil fire burners with forced air The front door hinge mounted it s insulated inside with ceramic fiber to be...

Page 6: ...ar 3 3 3 Combustion s chamber lenght mm 400 490 540 Combustion s chamber volume dm 3 27 2 35 8 53 3 Smoke discharge mm 127 127 127 Smoke s exit temperature C 153 153 156 Combustion chamber pressure Pa...

Page 7: ...OILERS MOD SIMPLEX n 1460080EN 07 2009 6 2 2 CONTROL PANEL A Timer optional E Switch on off B Heating regulation thermostat F Heating thermometer C Safety thermostat manual reset G Hydrometer D Fuse H...

Page 8: ...the wiring suitable for the equipment and burner maximum power adsorption 3 1 BURNER MATCHING For installation of the burner the electrical connections and the necessary settings consult the burner i...

Page 9: ...uits the combustion chamber The fumes range cleaning it s more important only millimetres of soot increase the flue gas outlet temperature at least 30 C decreasing one percentage point of thermal effi...

Page 10: ...Phase LO Programming time phase TA Environment Thermostat optional CO Programming time contact F Fuse TM Anti condensation low point thermostat CR Heating circulating pump IL Switch on off BR Burner I...

Page 11: ...134 PADOVA ITALY Tel 39 049 601600 Fax 39 049 9301471 Technical specifications and measurements are not binding The Company reserves the right to make changes without prior notice We decline all respo...

Reviews: