3
[L1] -
L1 - N
Adjustment of current phase
position
4 PHASE V
[0°]
L1
-
[L1 - N]
Adjustment of voltage phase
position
Phase correction between voltage and current in the measuring
system. (see table 1 at page 18)
This setting allows to measure also in systems without neutral.
However, the measuring voltage may not exceed 300 V
(if necessary, a voltage converter must be used).
5 INTEGRATION TIME
[1] s
(1...255 sec.)
The integration time (the time required to form the mean values
of a measurement) can be changed for special applications.
6 TRIGGER VALUE
[66] %
(30...100 )
Threshold for switching on of next stage. It should not be changed
in the normal case!
7 SWITCHING POWER
max [100] kvar
(multiples of the smallest stage)
This factor specifies the maximum power which may be switched in
one switching step. It can be used to control the intelligent control
system, which switches several stages as a function of the power-
factor requirement.
8 PROGRAM LOCK
[NO]
(NO / YES )
9 CONTROL [3] PHASE
( 3/1 )
PHASE I
[0°]
Section 7 Initial operation
The controller must have been installed before being set up and
operated. All network-specific parameters are fully programmed as
described in Section 3.2 (Programming) by being entered in sequence
and stored. The controller is then set to automatic operation with the
operating mode key. It is now ready for operation.