- Page 6 -

STACKING PRO-JAX

®

 UNITS FOR ADDITIONAL HEIGHT

According to OSHA, all scaffolds must be restrained from tipping.  This can be accomplished in one 

of three ways:

  1.  For free standing scaffolds, the maximum platform height must not exceed 3 times* the narrowest 

base dimension.

  2.  Guying the scaffold.

  3.  Tying the scaffold to a wall or other solid structure.

*Federal OSHA allows a maximum platform height of 4 times the narrowest base dimension.  However, 

Bil-Jax

 recommends 

that the maximum height be limited to 3 times the narrowest base dimension on all Pro-Jax utility scaffolds.

When additional platform height is required on a free standing scaffold, outriggers may be used to 

extend the base dimensions.  

Bil-Jax

 has different size outriggers available for use with Pro-Jax 

units. 18” wide outriggers are for use with two-frame high scaffolds and 24” wide outriggers are for 

use with three-frame high scaffolds.

WARNING

Whenever Pro-Jax units are stacked, outriggers are required!  Do not use a 

Pro-Jax utility scaffold over 1 frame high without outriggers.  Failure to use 

outriggers will make scaffold more likely to tip over causing serious injury 

or death!!

BUILDING A TWO FRAME HIGH SCAFFOLD

Top View

Outrigger

Frame

Side View

Outrigger

Tighten

Securely

Frame

Leg

STEP THREE

 — 

Clamp outrigger to end frame at a 90

°

 

 angle to the side brace.  

Tighten clamp securely.  Clamp must be flush against scaffold leg and casters must be 

in contact with the surface.

STEP ONE

 — 

Erect the base 

unit (one frame high scaffold) by 

following the previous instruction.

STEP TWO

 — 

Install casters into all 

four (4) outriggers and secure with snap pin 

provided with each caster.  Set caster brake.

If the platform height needed is between 6’ and 11’ 6”, it will be necessary to install 18” wide 

outriggers and a second scaffold level prior to use.

STEP FOUR

 — 

Add 

second scaffold level by 

stacking end frame over 

insert pins in top of base 

unit end frames.  Secure 

in place with snap pins.

STEP FIVE

 — 

Install 

side braces (minimum two), 

platform, and guard railing at 

desired height per the previous 

instructions (Building a One 

Frame High Scaffold).