Operation of the flame amplifier
6-1
6
Operation of the flame amplifier
All installation and connection work may be carried out by
qualified and approved specialist staff only !
Prior to initial operation, all regulations and adjustment
parameters set up by the operating company of the
burner have to be observed !
For the operation of the flame amplifier, please observe
the separate operating instructions of the flame scanner !
6.1
Connection of the flame amplifier
Prior to the connection of the flame scanner and a slide-in
power supply unit to the flame amplifier, observe the
separate operating instructions of the flame scanner and
of the slide-in power supply unit !
6.2
Testing the flame amplifier
In order to ensure a correct operation, flame amplifier as
well as flame scanner have to be tested several times in
case of all applications by starting and stopping the
burner several times (the flame relay has to be switched
off reliably in all cases in which the flame is absent). Carry
out this test whilst several neighbouring burners are
started and stopped and different boiler outputs are used.
This is an indispensable pre-requisite for a safe and cor-
rect operation of the device !
Summary of Contents for 3016
Page 2: ...ii ...
Page 20: ...Safety 2 8 ...
Page 26: ...Technical data 3 6 ...
Page 34: ...Transport installation and connection 4 8 ...
Page 46: ...Maintenance and servicing 7 2 ...
Page 48: ...Failures 8 2 ...
Page 50: ...Order data 9 2 ...
Page 54: ...Accessories 10 4 ...
Page 55: ...Accessories 10 5 ...