9.  Lift  or  turn  the  remote  control`s  EMERGENCY  SWITCH-OFF  button  up  and 
push  the  green  start  button,  after  which  the  green  light  should  be  seen  in  the 
button. 
 
10. Test the functions of the machine with the remote control before mounting the 
workpiece.  

  rotation 

  tilt 

  lift 

 
11.  For  welding,  connect  the  ground  cable  to  the  ground  socket  located  in  the 
machine  frame.  The  machine  has  one  ground  socket.  If  you  weld  with  higher 
welding  current  that  500  amperes,  further  ground-connect  directly  to  the 
workpiece.  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
12.  After  you  have  checked  the  functions  of  the  machine,  you  may  mount  the 
workpiece to the T-slot in the table plate. The workpiece should be mounted on 
table plate in a way that the central mass of the workpiece is closest as possible 
to the center of the table plate. 
 
13. MAKE SURE THAT THE WORKPIECE IS WELL-MOUNTED IN THE TABLE 
PLATE. 
 
14.  Make  sure  that  there  is  sufficient  free  space  to  handle  the  workpiece.  Do 
consider the trajectories of the workpiece in different positions of the table plate.. 
 
15.  You  may  begin  working  with  the  machine,  but  please  continuously  observe 
the functions of the machine and the mounting of the workpiece.   
 
17. After you have finished working with the workpiece, switch the machine off. 
 

Summary of Contents for Bestis 1000

Page 1: ...Bestis 1000 10000 User and Maintenance Manual Version 1 5...

Page 2: ...MACHINE OR A REPRESENTATIVE OF THE MANUFACTURER BESTEAM OY Nyrhintie 7 FIN 28760 PORI Tel 02 631 9102 Fax 02 631 9101 Machine Description Bestis Welding Positioner Model Bestis Welding Positioner The...

Page 3: ...oad calculation 14 5 ERROR NOTIFICATIONS 15 5 1 The machine s start button s light is blinking rapidly 15 5 2 The machine s start button s light is blinking slowly 15 5 3 The machine s start button s...

Page 4: ...ECTION CHECK THE SUFFICIENT GROUND CONNECTION OF THE WORKPIECE BEFORE BEGINNING TO WELD THE MANUFACTURER IS NOT RESPONSIBLE FROM CONSEQUENCES RESULTING FROM AN ABSENCE OF GROUND CONNECTION NOR INSUFFI...

Page 5: ...e three axis setting height tilt angle and rotation The rotation height adjustment and tilting are carried out by operating with light weight remote control All the models have been manufactured in ac...

Page 6: ...id work safety regulations 2 Before starting the machine it must be attended that the work area contains no people who have not been assigned to work with the machine nobody is looking directly at the...

Page 7: ...the machine and check its visible condition You are allowed to operate and store the machine in humidity controlled facilities with a temperature over 10 C 3 2 Deployment READ THE FOLLOWING NOTIFICAT...

Page 8: ...at is constructed from unbreakable concrete whose material strength is 30 N mm minimum 2 Make sure that there is a sufficient working space around the machine Also notify the shapes and dimensions of...

Page 9: ...ter you have checked the functions of the machine you may mount the workpiece to the T slot in the table plate The workpiece should be mounted on table plate in a way that the central mass of the work...

Page 10: ...table plate when demounting the workpiece Demount the fixtures and lift the workpiece from the table plate with care after making sure that the workpiece is no more mounted in the table plate 19 Clea...

Page 11: ...ods for example using right sized T slot nuts Make sure that the mounting is firm throughout the working process Secure the mounting regularly 4 2 Controlling devices 4 2 1 Main central 1 Main switch...

Page 12: ...r located in the front end of the remote The continuous rotation is stopped by pressing buttons 5 6 or The continuos anticlockwise rotation can be employed by following the procedure above in reverse...

Page 13: ...itch is connected to ON OFF position By pressing the pedal the rotation goes on and by pressing the pedal again the rotation goes off You can change the rotation direction by using the remote control...

Page 14: ...e in the permitted area seen as grey area in the chart The load moment must always be calculated from the center of the table plate to the center mass of the workpiece The mass centre is the point for...

Page 15: ...rts to blink slowly some of the following alarms are valid 1 a hydraulic motor has become overloaded check the thermal shield in the main central 2F1 2 temperature of the hydraulic oil is too high wai...

Page 16: ...l condition functioning of the motors suitability of the workplace abnormal tremor and sounds overheating that the protection and safety structures are on place and in appropriate condition that the h...

Page 17: ...the T slot in the table plate Also check that the bolts in the table plate and in the external gear are tight If you ll observe the bolts loosen these bolts should be replaced Before replacing the bol...