42-3/8" Long 2x3

Step 13 Install Rear Gable Trim

1

Install (4) four small OSB fillers, packed with

the hardware, over the 2x4 soffit blocks. Fillers
will be flush with the gable siding. Use 6d
common nails.

OSB Siding Filler

4.

Gather (2) two 82-1/2" long 1x4 trim boards. Butt

each board against the keystone and flush with the
top of the gable frame. Use 6d galv. nails.

Side Wall

Back Wall

The front able trim will be installed
in a later step.

Keystone

82-1/2" Long 1x4 Trim

Rear Gable

2.

Install (4) four 42-3/8" long 2x3 boards

on the rear gable flush with the top of
the gable frame. Use 10d sinkers

3.

Install a 8-1/2" long trim board,

called a keystone, at the top of the
gable flush with the top of the
gable frame. Use 6d galv. nails.

Summary of Contents for Greenbriar II 12x24

Page 1: ... not be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright 2018 Greenbriar II Building Size 12 x24 Revised July 19 2019 Assembly Book Manufactured by Reynolds Building Systems Inc 205 Arlington Drive Greenville PA 16125 800 245 1577 ...

Page 2: ...ood flooring is sold optionally You may choose to build your own or pour a cement pad Terminology Square Confirm corners are at 90 degrees Plumb Confirm walls and trusses are straight vertically Wall Plate Top and bottom 2x4s used to frame walls Tie Plate 2x4s connecting wall sections together Header Spans top of door opening OSB Oriented Strand Board LAP Edge of siding that overlaps Tongue Tongue...

Page 3: ...12 Treated Runner Foundation size is 12 0 x 24 0 Check local building codes in your area the construction may have to change For a concrete slab install sill sealer as a moisture barrier between the concrete and the wall plates Foam sill sealer can be purchased at home centers in rolls 3 1 2 or wider 1 Cut 2 two 2x4 12 to a length of 12 0 They will be used for the joist headers Layout from the lef...

Page 4: ... Studs 1 Cut 2 two 2x4 12 to a length of 140 1 2 Position the boards together and indicate with X marks where the wall studs will be located Stud Spacing Top Wall Plate Treated Bottom Plate Do not discard any material until construction is complete including short 2x4 blocks 99 Long 2x8 Step 2 Assemble Door Header 1 Locate 2 two 2x8 10 boards Cut these boards to a length of 99 2 Assemble the door ...

Page 5: ...opposite corners These measurements will be the same if the wall is square 4 Install the first Oriented Strand Board OSB panel flush with the side of the wall stud and flush with the top 2x4 plate Nail siding with 6d common nails spaced 8 apart Cut the OSB flush with the 2x4 bottom plate if you are installing the building on a concrete slab 5 Install 2 two more OSB panels Flush to Top 144 Treated ...

Page 6: ...and indicate with X Marks where the wall studs will be located 82 Header Support nail nail 2x4 Block Centered 2x8 Door Header 96 Finished Door Opening 21 21 Treated Bottom Plate 2 Install 4 four pre cut wall studs between the wall plates where shown Nail top plate to studs using 10d sinkers Nail bottom plate to studs using 16d galv nails 96 Door Opening 3 Cut 2 pre cut studs to a length of 82 and ...

Page 7: ... with the back wall 2x4 frame and flush with top plate Nail OSB to back wall and all 2x4s using 6d common nails spaced 8 apart 3 Install 5 five more OSB panels The last 24 wide panel will extend 3 1 2 past wall to receive front wall panel 4 Start at back wall and OSB siding to opposite wall 5 Erect front wall panel and secure corners with 10d sinkers Nail OSB to front wall 6 Cut and remove bottom ...

Page 8: ...angle cut at one end Nail through the bottom plate with 10d sinkers and secure the top with barbed metal drive on plates Step 6 Assemble Roof Gables 23 1 2 Gable Stud Bottom Gable Plate Barbed Metal Plate 80 1 2 long 2x4 Truss Rafter 2x4 Block 2x4 Block 6 Secure the 2x4 bottom plate to the truss rafter with a 2 1 2 wood screw on both ends Set gable aside 7 Repeat steps to assemble another gable 1 ...

Page 9: ... rafter and collar tie in place See Detail B 2 Secure the 2x4 truss rafters at the top with a 8 x 20 wood gusset Apply wood glue between the 2x4s and the gusset Nail the gusset to the 2x4s with 14 fourteen 6d common nails 3 Install 2 two 12 x24 gussets at ends of the collar tie Glue and nail using 14 nails per gusset 4 Turn this truss over and apply wood gussets to the opposite side 5 Repeat to as...

Page 10: ...he front and back wall Cut the last filler to fit between the soffit on the sidewalls Front Wall Door Opening 7 Soffit 3 1 2 Filler Tongue Edge Flush 1 Install a 7 wide x 48 3 4 siding panel over the side wall with the primed side facing down The tongue edge should be flush with front wall plate NOT over OSB Tack the soffit with a couple 6d common nails Installing 2x4 tie plates in a later step wi...

Page 11: ...other 2x4x12 Cut length to fit against gable on front wall Use 10d sinkers 2x4 12 2 Repeat to install tie plates on the opposite side wall Step 10 Install Siding on Gables 1 Locate pre cut gable OSB Install OSB above the lower OSB wall panels and flush with ends of gable frame Use 6d common nails 2 Repeat to install siding on the other gable frame ...

Page 12: ...ith 1 1 2 hanger nails The opening should line up with the X mark the bottom of the opening flush with the 2x4 tie plate Detail D 24 19 Measure from Backside of 2x4 Detail D 2x4 Tie Plate 3 Set roof trusses Secure trusses to metal hangers with 1 1 2 hanger nails 2x4 Block with Gable Frame Inside of Building 2x4 Block 4 Gather 22 twenty two short 2x4 blocks and install one at both ends of each trus...

Page 13: ...ds Butt each board against the keystone and flush with the top of the gable frame Use 6d galv nails Side Wall Back Wall The front able trim will be installed in a later step Keystone 82 1 2 Long 1x4 Trim Rear Gable 2 Install 4 four 42 3 8 long 2x3 boards on the rear gable flush with the top of the gable frame Use 10d sinkers 3 Install a 8 1 2 long trim board called a keystone at the top of the gab...

Page 14: ... Fascia 2x4 Truss Roof Sheathing 2x4 Tie Plate 2x4 Soffit Block Detail E 1x4 6 Fascia Board Straight Edge Nail Fascia to 2x4 Block 6 1 4 1 Install 4 four 42 3 8 long 2x3 boards on the front gable flush with the top of the gable frame Use 10d sinkers 1 Install a 1x4 4 white pine fascia board against the rear gable trim Install the fascia so the bottom edge of the roof sheathing will rest on the edg...

Page 15: ...th soffit panels The roof sheathing will extend 3 4 past the 2x3s to allow for trim Front Gable Step 16 Install Front Soffit Nail with 7d Sinkers 7 Wide Soffit Panels 42 3 8 Long 2x3 Sheathing Projects 3 4 Upper Roof Sheathing 42 3 8 Long 2x3 3 Repeat on other side Sheets should meet at center of trusses when installed 48 x 72 48 x 48 48 x 82 3 4 36 1 2 x 96 36 1 2 x 72 1x4 6 36 1 2 x 34 3 4 48 x ...

Page 16: ...of the door opening flush with the front wall OSB Cut 2nd piece to fit Use 6d galv nails Step 18 Install 2x4s Around Door Jamb Prime Door Jamb 2x4 Cut to Fit 51 1 2 Long 2x4 1 Select 2 two 2x4s Cut each to fit on either side of door opening against back of jamb Secure to stud with 10d sinkers 2 Select 2 two 2x4s and cut each to 51 1 2 long Install across top jamb and 2x4s Secure to header with 10d...

Page 17: ...le Door Trim 1 Install a keystone and gable trim under the roof sheathing as done in Step 13 Keystone 2 Measure from bottom of OSB to bottom of door header Cut 2 two 1x4 8 trim boards to this length and install boards to the sides of the door opening flush with jamb Use 6d galv nails 3 Cut a 1x4 10 trim board to 105 in length and install centered across the top of the side door trim ...

Page 18: ...s instructions If you ordered the optional floor install the galvanized door sill Secure sill with pan head screws Galv Door Sill Install Optional Door Sill Step 21 Install Roofing Not Supplied in Kit 1 Install metal roof edging along the end walls and the front edge of the roof sheathing Roof Sheathing 1x4 Trim Metal Roof Edge ...

Page 19: ...ccording to the manufacturer s instructions Vinyl Siding Not Supplied in Kit 1x4 Door Trim J Channel Material List for Vinyl Siding 5 1 2 sq Vinyl Siding double 4 standard profile 4 ea Outside Corners 5 ea J Channel 5 ea Under Sill Trim 6 ea Starter Strips 3 lb Nails ...

Page 20: ...7 16 20 x 48 2 ea Sheathing 7 16 48 x 40 angled 4 ea Sheathing 7 16 48 x 28 angled 2 ea Sheathing 7 16 48 x 82 3 4 2 ea Sheathing 7 16 48 x 72 2 ea Sheathing 7 16 36 1 2 x 72 2 ea Sheathing 7 16 36 1 2 x 48 2 ea Sheathing 7 16 36 1 2 x 34 3 4 4 ea OSB Fillers 7 16 2 x 3 1 2 2 ea Header Filler 7 16 7 1 4 x 48 2 ea Door Jamb 3 8 5 3 8 x 48 2 ea Door Jamb 3 8 5 3 8 x 84 44 pcs 2x4 Pre cut Wall Studs ...