Step 12B
Install Gable Siding continued
Step 13
Install Gable Overhang
4.
Install last siding panel.
3.
Install center siding. If you purchased a sunburst window you may cut the opening in the
siding at this time. Instructions are packed in the window box. It is advisable to install the
window after the gable is set
30-3/4" Long 2x4
77-3/8" Long 2x4
Do not remove the temporary 1x4 blocks until
the roof trusses and back gable are assembled.
1.
Locate (2) two 77-3/8" long 2x4 rafters on gable. Install 2x4s flush with the top of gable
frame. Use 10d sinkers.
2.
Locate (2) two 30-1/4" long 2x4 rafters and install to finish. 2x4s will extend beyond end of
gable.