background image

3 | COMMISSIONING AND MAINTENANCE

24

Refrigerant label

In base alla Normativa CE n. 517/2014 su determinati gas florurati ad
effetto serra, è obbligatorio indicare la quantità totale di refrigerante
presente sistema installato. Tale informazione è presente nella targhetta
tecnica presente nell'unità esterna.

A

Standard charge

B

Additional charge

C

Total charge

D

Equivalent total weight of CO2

To write the tag:

- note the quantity onto the label with indelible ink
- place the refrigerant gas label on the outdoor unit

This unit contains fluorinated greenhouse gases covered by the
Kyoto protocol. Maintenance and disposal activities must be carried
out exclusively by skilled personnel.

Global warming potential of the R32 refrigerant gas: GWP=675

If necessary, the refrigerant must be recovered and not dispersed
into the environment.

It is forbidden to disperse the refrigerant into the environment.

3.3

Ordinary maintenance

Routine maintenance is fundamental for keeping the equipment efficient,
safe and reliable. It can be performed periodically by the Technical
Support Service, whose staff is technically qualified and can use genuine
spare parts, if necessary.

For units installed in a seaside environment, the maintenance
intervals shall be halved.

Original conditions must be restored after performing the required
maintenance operations.

All described operations MUST be carried out under the following
conditions:

- cold device
- device NOT supplied with electric power
- suitable personal protection equipment

Do not open the access covers and carry out technical or cleaning
activities before disconnecting the unit from the power grid by
positioning the system's main switch in the "OFF" position.

- position the system's main switch in the "OFF" position.

Wait 10 minutes before touching the device electric components.

Check with a tester that the voltage between the power supply
connectors of the main electronic board is lower than 10 Vdc.

Yearly operations

The annual maintenance plan includes the following checks:

- power supply voltage
- electric connection tightening
- status of cooling and hydraulic joint
- finned coil cleaning
- electric absorption
- fan grille cleaning

Cleaning the heat exchanger fins

The thermal exchange bank must be cleaned with compressed air.
Cleaning must be carried out at least once a year, according to the
location of the unit, as dirt accumulating between the fins narrows the
passage section and reduces the exchange capability.

- check the alignment of the bank's aluminium fins and, if

necessary, straighten them with the appropriate comb

- check that the condensate discharge pipe is clean

Do not use any means to accelerate the defrosting.

Do not use systems different from the ones indicated in this manual.

Emptying of the evaporator

This operation may be necessary to perform reparations on the low
pressure side (evaporator), the device reallocation or the replacement of
the indoor unit without losing the whole refrigerant charge.
Proceed as follows:

- remove the covering plug from the shut-off valve
- check that the three-way shut-off valve is fully open
- let the device operate in cooling mode for 10 - 15 minutes
- stop the device for about 3 minutes
- connect the charging tube of the pressure gauge unit to the

three-way valve service connection on gas side

- vent the air from the charging tube
- close the two-way shut-off valve on liquid side
- operate the equipment in cooling mode until pressure gauge

reads a suction pressure of approx. -1 MPa

- close the three-way shut-off valve on gas side
- stop the unit
- disconnect the pressure gauge unit
- refit the valve covering plug

Carefully check for absence of leakages from the closing point of the
plug.

3.4

Segnalazione di funzionamento e allarmi

Signals are displayed by means of LEDs on the unit main electronic
board.
Proceed as follows to access the filters:

Summary of Contents for 20171581

Page 1: ...Installer manual BREVA EX EN...

Page 2: ...Thank you again and keep up the good work BERETTA S p A COMPLIANCE BREVA EX heat pumps are compliant with the following European Directives Low Voltage Directive 2014 35 EU Electromagnetic Compatibil...

Page 3: ...3 Ordinary maintenance 3 4 Segnalazione di funzionamento e allarmi 4 DISPOSAL The following symbols are used on the product The R32 refrigerant gas is slightly inflammable and odourless Avoid proximi...

Page 4: ...rigerant gas operate carefully so as to avoid damaging the gas circuit and the fin bank Do not place any inflammable object spray cans within a 1 metre radius from the air expulsion According to EU Re...

Page 5: ...ti freeze sensor which transmits the temperature value as detected by the heat exchanger to the electronic board that is triggered when the heat exchanger is clogged by frost formations outdoor air te...

Page 6: ...ling 10 Liquid line connection 16 Electric panel cover 5 Heat exchanger 11 Muffler 6 Electric fan 12 Filter MODEL 12000 1 1 Upper panel 6 Electric fan 13 Filter 2 Fan protection grille 8 Rotary compre...

Page 7: ...16 Terminal board for electric connections 5 Handle for handling 11 Liquid line connection 17 Electric panel cover 6 Heat exchanger 12 Muffler MODEL 24000 1 1 Upper panel 6 Electric fan 11 Filter 2 Fa...

Page 8: ...apacity at rated air flow kW 2 90 3 70 5 20 8 10 Absorbed power at rated air flow kW 0 78 0 99 1 40 2 18 COP kW kW 3 71 3 71 3 71 3 71 Capacity at maximum air flow kW 3 80 4 60 6 00 10 00 Absorbed pow...

Page 9: ...um current consumption A 1 40 1 80 2 30 3 20 Electrical characteristics Power supply V Ph Hz 230 1 50 230 1 50 230 1 50 230 1 50 Compressor Compressor Tipo Rotary Rotary Rotativo Doppio Rotativo Doppi...

Page 10: ...the air inside the rooms During the wintertime the heat pump extracts the thermal energy from the outdoor air and delivers it to the room air thereby heating it During the summertime the cycle is rev...

Page 11: ...ion s book for the installer and for the Technical Service in English Warranty Spare parts labels energy label etichetta gas refrigerante contact sheet It is also supplied as kit Condensate discharge...

Page 12: ...cking material must not be disposed of in the surrounding environment and must be kept out of children reach as it can be dangerous It must be disposed of according to the regulations in force 2 6 Pla...

Page 13: ...osition so as to prevent the air flow from being blocked or install a roofing to protect it Adequate anti freeze systems should be used for installations in extremely cold areas where there is a possi...

Page 14: ...turer shall bear no responsibility for any damages caused by incorrect system installation 2 10 Refrigerating connection The dimensions and positions of cooling connections are shown hereunder MODELLO...

Page 15: ...lare connections Cooling lines must be as straight as possible and any necessary bends must have a radius grater than 40 mm Use clean hoses Make sure the inside is free of dust residues water Avoid th...

Page 16: ...insulating material on the joints Pipe insulation Connection pipes must be thermally insulated to prevent dispersions of heat or formation of condensate 1 Gas pipe 2 Condensation discharge 3 Liquid p...

Page 17: ...rating circuit as they can cause explosions reach a pressure equal to 0 3 Mpa wait 3 minutes check that the pressure has not dropped reach a pressure equal to 1 5 Mpa wait 3 minutes check that the pre...

Page 18: ...pipes If the pressure has not risen again A Opening B Closing 1 Service connection blanking plug 2 On off valve shaft 3 Refrigerating pipe attachment 4 On off valve cover plug 5 Hex wrench remove the...

Page 19: ...2 INSTALLATION 19 2 11 Wiring diagram MODEL 9000 1 MODELLO 12000 1 18000 1...

Page 20: ...red with a separate electric circuit 1 Electric connection input position the system s main switch in the OFF position Wait 10 minutes before touching the device electric components To access the term...

Page 21: ...For the sizing of the electrical power cables and safety devices use the following table Model 9000 1 12000 1 18000 1 24000 1 Electrical characteristics Protection factor IP X4 X4 X4 X4 Protection aga...

Page 22: ...ds contact opening of at least 3 mm with adequate breaking power and differential protection installed near the equipment connect the device to a properly functioning earthing system make sure that th...

Page 23: ...ted controls have problems turn the device off and call the Technical Service immediately Do not touch the device pipes to prevent potential burns Take anti static precautions in case of weather condi...

Page 24: ...ck with a tester that the voltage between the power supply connectors of the main electronic board is lower than 10 Vdc Yearly operations The annual maintenance plan includes the following checks powe...

Page 25: ...blinking After the LED switches off Wait 10 minutes before touching the device electric components Check with a tester that the voltage between the power supply connectors of the main electronic boar...

Page 26: ...temperature sensor failure The alarm activates 4 minutes after the unit start After 3 consecutive interventions in 30 minutes the unit resets after problem resolution 14 Compressor suction overtemper...