Installation and Operation Manual

   

Solar  |  solar storage cylinder

IDRA N DS

Installation and Operation Manual

EN

   

Summary of Contents for 20086803

Page 1: ...Installation and Operation Manual Solar solar storage cylinder IDRA N DS Installation and Operation Manual EN...

Page 2: ...2...

Page 3: ...following symbols are used in this manual b CAUTION Identifies actions that require caution and adequate preparation a STOP Identifies actions that you MUST NOT do This manual Code Rev comprises pages...

Page 4: ...acement immediately Keep the product purchase documents to be present ed to the B authorised Technical Assistance Centre to request a service call under warranty b Size the solar expansion tank so as...

Page 5: ...t 20052790K4LH3800001 Model IDRA N DS 1500 Code 20052790 Serial Number K4LH3800001 Beretta Caldaie Via Risorgimento 13 23900 Lecco LC Italy Capacit nom sanitaria 1449 L 1 8 mq 3 4 mq 1200 L h 2200 L h...

Page 6: ...Sleeve for electric heating element 1 1 2 Coil water capacity 19 4 28 1 28 4 L Coil heat exchange surface area 3 4 4 6 4 6 m2 Power absorbed by coil 88 120 110 kW Domestic hot water production 2200 29...

Page 7: ...ders are equipped with ded icated sockets for the storage cylinder TEMPERATURE GAUGE or TEMPERATURE SENSOR b The installer is responsible for making all necessary connections to the boiler and solar c...

Page 8: ...1 2 F 1 1 4 F Psc1 Diameter length of boiler sensor socket 8 200 mm Psc2 Diameter length of boiler sensor socket 8 200 mm Psr Diameter length of solar controller sensor socket 8 200 mm RE Sleeve for e...

Page 9: ...it safe MODELS IDRA N DS 2000 B IDRA N DS storage cylinders come in two separate packages The first contains the painted cylinder protected by a plastic bag and supported on a wooden pallet The secon...

Page 10: ...equipment and use suitable safety devices b Make sure that any lifting equipment is of adequate capacity to lift and move the storage cylinder a Do not dispose of packaging material into the envi ron...

Page 11: ...storage cylinder from the pallet cut the straps secure the lifting cables to the lifting points on the top of the storage cylinder carefully lift the storage cylinder and position it as re quired 11...

Page 12: ...npack all the material from the second package Wrap the insulation 3 around the storage cylinder carefully lining up the fittings with the holes on the inside of the insulation Secure the insulation i...

Page 13: ...orage cylinder is to be installed 14 INSTALLATION IN OLDER SYSTEMS AND SYSTEMS REQUIRING MODERNISATION When installing B IDRA N DS storage cylinders in old systems or systems requiring modernisation a...

Page 14: ...ake sure that all circuits have been bled Make sure that the boiler and solar collectors con nected to the system shut down correctly when their mains power switches are turned OFF Provided the above...

Page 15: ...e cylinder after cleaning it a Do not use abrasive products petrol or triethylene INTERNAL CLEANING Removing and checking the magnesium anode Remove the cap 1 cover 2 and the anode insula tor disc 1 2...

Page 16: ...functioning Check the pump The water temperature from the boiler is too low Check the temperature setting There is air in the primary circuit Bleed the circuit SOLAR COLLECTOR CIRCUIT FAULT CAUSE SOLU...

Page 17: ...the environmental impact and save energy in case of brief absences week ends short trips etc and with external temperatures above 0 C set the heater tem perature control where available to the minimu...

Page 18: ...END USER 18...

Page 19: ...END USER 19...

Page 20: ...23 A 23900 Lecco LC www berettaboilers com The manufacturer strives to continuously improve all products Appearance dimensions technical specifications standard equipment and accessories are therefor...