STEP 7
( Sheave Installation )
1. Inspect Cables to ensure proper lengths. All Cables
should have ID tags showing proper Cable lengths.
2. In order to install the Cables it is necessary to first
extend the Hydraulic Cylinder. Remove both Cylinder port
plugs then use a rubber tipped air gun or come-along to
extend the Cylinder. (See Fig. 7.1)
IMPORTANT! - Be careful not to damage the chrome rod
during this step.
3. You must reinstall the Sheaves and Pins in the same
order as they were removed. (See Fig. 7.2)
STEP 8
( Cable Installation )
1. Make sure the the window for the retaining nut and
Zerk fittings are facing down. (See Fig. 8.1)
2. Route the threaded Cable ends through the ends of
each Cross Tube. Care must be taken when routing the
Lifting Cables to ensure they are routed
below
the Cross
Tube Mounting Bolts. (See Fig 8.2)
3. Route Cables over the Slack Safety Sheaves then to
the top of each Column. Secure using the M18 Hex Head
Nuts and Flat Washers. (See Fig. 8.3)
Failure to route Lifting Cables as described may lead to
serious personal injury and/or death to operator or
bystander and/or may cause damage to property.
Fig 7.1
Fig 7.2
Fig 8.1
Fig 8.2
DO NOT PROCEED unless visual
confirmation is made of ALL Safety Locks.
ALL locks MUST be engaged before
proceeding. Failure to comply with these
instructions may result in severe personal
injury or death. (See page 13)
Summary of Contents for HD-7ZM
Page 26: ...26 ...
Page 35: ...35 ...
Page 36: ...36 ...
Page 44: ...44 ...
Page 45: ...45 ...
Page 46: ...46 ...
Page 47: ...47 ...
Page 48: ...48 ...
Page 49: ...49 ...
Page 50: ...50 ...
Page 51: ...51 ...
Page 52: ...52 ...
Page 53: ...53 MAINTENANCE RECORDS ...
Page 54: ...54 MAINTENANCE RECORDS ...
Page 55: ...55 NOTES ...
Page 56: ...56 ...